Energy Projects Near You

North Court Farm, Chilham Solar Farm (44 MW)

North Court Farm, Chilham Solar Farm is a 44 MW solar farm project in Ashford, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 31 October 2025; the record was last updated on 3 May 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

44 MWsolar farm
refused on appealstatus in REPD
3 May 2024record last updated
Ashfordcouncil area

Planning timeline

DateStage
25 October 2022Application submitted
18 April 2024Refused by the planning authority
31 October 2025Appeal refused
31 October 2025Secretary of State refused

Project details

Technology
solar farm
Capacity
44 MW
Status (REPD)
refused on appeal
Record last updated
3 May 2024
Operator or applicant
GSI North Court Limited
Planning authority
Ashford
Planning application reference
PA/2022/2415
Site area
47.6 ha
Address (REPD)
North Court Farm, Lower Lees Road, Chilham, Canterbury
Council area (by location)
Ashford
Time to decision
77 weeks
Name in REPD
North Court Farm, Chilham - Solar Farm
REPD reference
9868

Who decides

ApplicationsAshfordUK
Decided applications (solar, wind, battery)3010,236
Refused8 (27%)19%
Solar refused6 of 2112%
Battery storage refused2 of 916%
Median time from submission to decision12.7 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Littles Manor Farmsolar farm9.5refused on appeal7.4
Nackington Farm Solar Park- Site Csolar farm12application withdrawn8.0
Nackington Farm Solar Park- Site Bsolar farm16.6application withdrawn8.0
Nackington Farm Solar Park- Site Asolar farm11application withdrawn8.4
Abbey Fields Farmsolar farm5.3operational8.4
Britton Court Farm, Hackington Road Solar Farmsolar farm38approved, not built9.4
Cleve Hill Solar Projectsolar farm373operational10.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.2569, 0.9728).