Energy Projects Near You

Cleve Hill Solar Project (373 MW)

Cleve Hill Solar Project is a 373 MW solar farm project in Swale, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 July 2025; the record was last updated on 28 July 2025. As a nationally significant project, it was decided by the Secretary of State responsible for energy at the time on a Development Consent Order after examination by the Planning Inspectorate (EN010085).

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

373 MWsolar farm
operationalstatus in REPD
28 July 2025record last updated
Swalecouncil area

Planning timeline

DateStage
16 November 2018Application submitted
28 May 2020Refused by the planning authority
29 January 2021Development consent granted (Secretary of State)
1 April 2023Construction started
1 July 2025Operational

Project details

Technology
solar farm
Capacity
373 MW
Status (REPD)
operational
Record last updated
28 July 2025
Operator or applicant
Quinbrook Infrastructure Partners
Planning authority
The Planning Inspectorate - National Infrastructure
Planning application reference
EN010085
Site area
364.0 ha
Address (REPD)
Graveney, Whitstable
Council area (by location)
Swale
Time to decision
115 weeks
Contracts for Difference
AR4
REPD reference
6502

The scheme also includes 150 MW of battery storage, recorded separately in REPD (operational).

Official project record at the Planning Inspectorate (EN010085)

Who decides

As a nationally significant project, it was decided by the Secretary of State responsible for energy at the time on a Development Consent Order after examination by the Planning Inspectorate (EN010085). All Energy Secretary decisions on solar and wind farms. The Planning Inspectorate - National Infrastructure refused 7% of 46 decided solar, wind and battery applications in REPD (median 73 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Abbey Fields Farmsolar farm5.3operational2.4
Littles Manor Farmsolar farm9.5refused on appeal5.9
Old Rides solar Farmsolar farm8operational6.8
Old Rides Farm, Leysdown Roadbattery storage1,000application submitted7.2
New Rides Wind Farmwind farm8.8operational7.3
New Rides Farm - Photovoltaic Panelssolar farm10approved, not built7.4
Tonge Corner Farmsolar farm22operational9.4
North Court Farm, Chilham Solar Farmsolar farm44refused on appeal10.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.3388, 0.9139).