New Rides Wind Farm (8.8 MW)

New Rides Wind Farm is an 8.8 MW wind farm project in Swale, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 December 2018; the record was last updated on 29 May 2019.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8.8 MWwind farm
operationalstatus in REPD
29 May 2019record last updated
Swalecouncil area

Planning timeline

DateStage
27 January 2014Application submitted
3 February 2015Refused by the planning authority
25 June 2015Appeal lodged
9 August 2017Planning permission granted
9 August 2017Appeal allowed
7 June 2018Construction started
1 December 2018Operational

Project details

Technology
wind farm
Capacity
8.8 MW
Status (REPD)
operational
Record last updated
29 May 2019
Operator or applicant
Airvolution Energy
Planning authority
Swale
Planning application reference
SW/13/1571
Appeal reference
APP/V2255/W/15/3014371
Turbines
4
Address (REPD)
New Rides Farm, Leysdown Road, Sheerness
Council area (by location)
Swale
Time to decision
184 weeks
REPD reference
4403

Who decides

ApplicationsSwaleUK
Decided applications (solar, wind, battery)4010,236
Refused5 (12%)19%
Solar refused4 of 3012%
Onshore wind refused1 of 345%
Battery storage refused0 of 716%
Median time from submission to decision15.1 weeks17.0 weeks
Appeals lodged / allowed3 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
New Rides Farm - Photovoltaic Panelssolar farm10approved, not built0.2
Old Rides solar Farmsolar farm8operational0.6
Old Rides Farm, Leysdown Roadbattery storage1,000application submitted1.1
South Lees Farmsolar farm11operational4.0
Land off Queenborough Roadbattery storage40under construction6.8
Cleve Hill Solar Projectsolar farm373operational7.3
Tonge Corner Farmsolar farm22operational7.3
Plot 2B EurolinkVbattery storage20under construction8.6
Ridham Avenue, Swale Way - Kemsley Battery Energy Storagebattery storage249approved, not built8.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.396, 0.8632).