Plot 2B EurolinkV (20 MW battery storage)

Plot 2B EurolinkV is a 20 MW battery storage project in Swale, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 October 2021; the record was last updated on 13 December 2021.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWbattery storage
under constructionstatus in REPD
13 December 2021record last updated
Swalecouncil area

Planning timeline

DateStage
3 May 2019Application submitted
25 July 2019Planning permission granted
1 October 2021Construction started

Project details

Technology
battery storage (stand-alone storage)
Capacity
20 MW
Status (REPD)
under construction
Record last updated
13 December 2021
Operator or applicant
Trenport Investments
Planning authority
Swale
Planning application reference
19/502257/FULL
Address (REPD)
Plot 2B Eurolink V, Sittingbourne, Land orth of Swale Way, Sittingbourne
Council area (by location)
Swale
Time to decision
12 weeks
REPD reference
7383

Who decides

ApplicationsSwaleUK
Decided applications (solar, wind, battery)4010,236
Refused5 (12%)19%
Solar refused4 of 3012%
Onshore wind refused1 of 345%
Battery storage refused0 of 716%
Median time from submission to decision15.1 weeks17.0 weeks
Appeals lodged / allowed3 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Tonge Corner Farmsolar farm22operational1.3
Ridham Avenue, Swale Way - Kemsley Battery Energy Storagebattery storage249approved, not built2.2
Kemsley Energy Park Battery Storagebattery storage120approved, not built2.8
Kemsley Substationbattery storage49.9operational2.9
Pitstock Farmsolar farm41approved, not built4.5
Orchard Farmsolar farm10operational5.5
Raspberrysolar farm49.9approved, not built5.7
Bobbing solar farmsolar farm11.3operational5.7
Vigo Lane, Borden Solar Farmsolar farm40approved, not built6.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.3463, 0.7693).