Kemsley Energy Park Battery Storage (120 MW)

Kemsley Energy Park Battery Storage is a 120 MW battery storage project in Swale, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 30 September 2024, not yet built; the record was last updated on 10 November 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

120 MWbattery storage
approved, not builtstatus in REPD
10 November 2025record last updated
Swalecouncil area

Planning timeline

DateStage
16 March 2023Application submitted
30 September 2024Planning permission granted
30 September 2027Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
120 MW
Status (REPD)
approved, not built
Record last updated
10 November 2025
Operator or applicant
FPC Electric Land limited
Planning authority
Swale
Planning application reference
23/500771/FULL
Address (REPD)
The West Of Barge Way
Council area (by location)
Swale
Time to decision
81 weeks
REPD reference
13489

Who decides

ApplicationsSwaleUK
Decided applications (solar, wind, battery)4010,236
Refused5 (12%)19%
Solar refused4 of 3012%
Onshore wind refused1 of 345%
Battery storage refused0 of 716%
Median time from submission to decision15.1 weeks17.0 weeks
Appeals lodged / allowed3 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Kemsley Substationbattery storage49.9operational0.2
Ridham Avenue, Swale Way - Kemsley Battery Energy Storagebattery storage249approved, not built0.6
Tonge Corner Farmsolar farm22operational2.8
Plot 2B EurolinkVbattery storage20under construction2.8
Orchard Farmsolar farm10operational3.2
Raspberrysolar farm49.9approved, not built3.4
Bobbing solar farmsolar farm11.3operational4.0
Land off Queenborough Roadbattery storage40under construction4.9
South Lees Farmsolar farm11operational5.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.3668, 0.7448).