Bobbing solar farm (11.3 MW)

Bobbing solar farm is an 11.3 MW solar farm project in Swale, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2016; the record was last updated on 1 April 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11.3 MWsolar farm
operationalstatus in REPD
1 April 2016record last updated
Swalecouncil area

Planning timeline

DateStage
6 May 2014Application submitted
20 October 2014Refused by the planning authority
22 June 2015Appeal lodged
7 December 2015Planning permission granted
7 December 2015Appeal allowed
31 January 2016Construction started
31 March 2016Operational

Project details

Technology
solar farm
Capacity
11.3 MW
Status (REPD)
operational
Record last updated
1 April 2016
Operator or applicant
Solar Securities (Group)
Planning authority
Swale
Planning application reference
SW/14/0525
Appeal reference
APP/V2255/W/15/3017938
Site area
24.5 ha
Address (REPD)
Cold Harbour Lane, Bobbing, Sittingbourne, Kent
Council area (by location)
Swale
Time to decision
83 weeks
REPD reference
1970

Who decides

ApplicationsSwaleUK
Decided applications (solar, wind, battery)4010,236
Refused5 (12%)19%
Solar refused4 of 3012%
Onshore wind refused1 of 345%
Battery storage refused0 of 716%
Median time from submission to decision15.1 weeks17.0 weeks
Appeals lodged / allowed3 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Orchard Farmsolar farm10operational1.5
Raspberrysolar farm49.9approved, not built1.5
Kemsley Substationbattery storage49.9operational3.9
Kemsley Energy Park Battery Storagebattery storage120approved, not built4.0
Ridham Avenue, Swale Way - Kemsley Battery Energy Storagebattery storage249approved, not built4.2
Vigo Lane, Borden Solar Farmsolar farm40approved, not built4.2
Plot 2B EurolinkVbattery storage20under construction5.7
Tonge Corner Farmsolar farm22operational6.4
Pitstock Farmsolar farm41approved, not built7.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.3581, 0.6889).