Vigo Lane, Borden Solar Farm (40 MW)

Vigo Lane, Borden Solar Farm is a 40 MW solar farm project in Swale, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 1 September 2025, not yet built; the record was last updated on 16 September 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

40 MWsolar farm
approved, not builtstatus in REPD
16 September 2025record last updated
Swalecouncil area

Planning timeline

DateStage
5 May 2023Application submitted
9 August 2024Refused by the planning authority
1 September 2025Planning permission granted
1 September 2025Appeal allowed

Project details

Technology
solar farm
Capacity
40 MW
Status (REPD)
approved, not built
Record last updated
16 September 2025
Operator or applicant
Industria Solar Vigo (Industria Brand Energy)
Planning authority
Swale
Planning application reference
23/502210/FULL
Site area
61.4 ha
Address (REPD)
Vigo Lane Borden
Council area (by location)
Swale
Time to decision
121 weeks
Name in REPD
Vigo Lane, Borden - Solar Farm
REPD reference
10695

Who decides

ApplicationsSwaleUK
Decided applications (solar, wind, battery)4010,236
Refused5 (12%)19%
Solar refused4 of 3012%
Onshore wind refused1 of 345%
Battery storage refused0 of 716%
Median time from submission to decision15.1 weeks17.0 weeks
Appeals lodged / allowed3 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bobbing solar farmsolar farm11.3operational4.2
Pitstock Farmsolar farm41approved, not built4.4
Orchard Farmsolar farm10operational5.6
Raspberrysolar farm49.9approved, not built5.7
Ridham Avenue, Swale Way - Kemsley Battery Energy Storagebattery storage249approved, not built6.3
Plot 2B EurolinkVbattery storage20under construction6.3
Kemsley Substationbattery storage49.9operational6.4
Kemsley Energy Park Battery Storagebattery storage120approved, not built6.5
Tonge Corner Farmsolar farm22operational7.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.3199, 0.6884).