Kemsley Substation (49.9 MW battery storage)

Kemsley Substation is a 49.9 MW battery storage project in Swale, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 25 October 2021; the record was last updated on 9 March 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
operationalstatus in REPD
9 March 2026record last updated
Swalecouncil area

Planning timeline

DateStage
24 May 2019Application submitted
20 September 2019Planning permission granted
15 November 2019Construction started
25 October 2021Operational

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
operational
Record last updated
9 March 2026
Operator or applicant
Pivot Power
Planning authority
Swale
Planning application reference
19/502514/FULL
Address (REPD)
Land To The South Of Kemsley S, Ypres Drive, Kemsley, Sittingbourne, Kent
Council area (by location)
Swale
Time to decision
17 weeks
REPD reference
7368

Who decides

ApplicationsSwaleUK
Decided applications (solar, wind, battery)4010,236
Refused5 (12%)19%
Solar refused4 of 3012%
Onshore wind refused1 of 345%
Battery storage refused0 of 716%
Median time from submission to decision15.1 weeks17.0 weeks
Appeals lodged / allowed3 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Kemsley Energy Park Battery Storagebattery storage120approved, not built0.2
Ridham Avenue, Swale Way - Kemsley Battery Energy Storagebattery storage249approved, not built0.7
Plot 2B EurolinkVbattery storage20under construction2.9
Tonge Corner Farmsolar farm22operational3.0
Orchard Farmsolar farm10operational3.0
Raspberrysolar farm49.9approved, not built3.2
Bobbing solar farmsolar farm11.3operational3.9
Land off Queenborough Roadbattery storage40under construction5.0
South Lees Farmsolar farm11operational5.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.3668, 0.7425).