Land off Queenborough Road (40 MW battery storage)

Land off Queenborough Road is a 40 MW battery storage project in Swale, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 December 2019; the record was last updated on 12 January 2021.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

40 MWbattery storage
under constructionstatus in REPD
12 January 2021record last updated
Swalecouncil area

Planning timeline

DateStage
8 June 2017Application submitted
12 October 2017Planning permission granted
1 December 2019Construction started

Project details

Technology
battery storage (stand-alone storage)
Capacity
40 MW
Status (REPD)
under construction
Record last updated
12 January 2021
Operator or applicant
UK Power Reserve
Planning authority
Swale
Planning application reference
17/503032/FULL
Address (REPD)
Land Adjacent To 9 Neatscourt Cottages, Queenborough Road, Halfway, Kent
Council area (by location)
Swale
Time to decision
18 weeks
REPD reference
7003

Who decides

ApplicationsSwaleUK
Decided applications (solar, wind, battery)4010,236
Refused5 (12%)19%
Solar refused4 of 3012%
Onshore wind refused1 of 345%
Battery storage refused0 of 716%
Median time from submission to decision15.1 weeks17.0 weeks
Appeals lodged / allowed3 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
South Lees Farmsolar farm11operational2.8
Port of Sheerness Wind Farm (was Lappel Bank)wind farm8.2operational4.1
Kemsley Energy Park Battery Storagebattery storage120approved, not built4.9
Kemsley Substationbattery storage49.9operational5.0
Ridham Avenue, Swale Way - Kemsley Battery Energy Storagebattery storage249approved, not built5.4
Power Station Road, Isle Of Grainbattery storage249approved, not built5.7
Tonge Corner Farmsolar farm22operational6.0
Orchard Farmsolar farm10operational6.5
Raspberrysolar farm49.9approved, not built6.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.4087, 0.7679).