South Lees Farm (11 MW solar farm)

South Lees Farm is an 11 MW solar farm project in Swale, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 22 June 2014; the record was last updated on 17 December 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11 MWsolar farm
operationalstatus in REPD
17 December 2014record last updated
Swalecouncil area

Planning timeline

DateStage
4 October 2013Application submitted
22 January 2014Planning permission granted
14 February 2014Construction started
22 June 2014Operational

Project details

Technology
solar farm
Capacity
11 MW
Status (REPD)
operational
Record last updated
17 December 2014
Operator or applicant
Solar Century
Planning authority
Swale
Planning application reference
SW/13/1202
Site area
19.0 ha
Address (REPD)
Land adjacent South Lees Farm, Lower Road, Minster On Sea, Sheerness, Kent
Council area (by location)
Swale
Time to decision
16 weeks
REPD reference
1767

Who decides

ApplicationsSwaleUK
Decided applications (solar, wind, battery)4010,236
Refused5 (12%)19%
Solar refused4 of 3012%
Onshore wind refused1 of 345%
Battery storage refused0 of 716%
Median time from submission to decision15.1 weeks17.0 weeks
Appeals lodged / allowed3 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land off Queenborough Roadbattery storage40under construction2.8
New Rides Wind Farmwind farm8.8operational4.0
New Rides Farm - Photovoltaic Panelssolar farm10approved, not built4.1
Old Rides solar Farmsolar farm8operational4.5
Old Rides Farm, Leysdown Roadbattery storage1,000application submitted5.0
Tonge Corner Farmsolar farm22operational5.5
Kemsley Energy Park Battery Storagebattery storage120approved, not built5.8
Kemsley Substationbattery storage49.9operational5.9
Ridham Avenue, Swale Way - Kemsley Battery Energy Storagebattery storage249approved, not built6.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.4017, 0.8064).