Solar, wind and battery projects near Gillingham (ME8)
27 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of ME8 (Medway): 19 approved but not yet running, 4 operational. The largest live scheme is Raspberry (49.9 MW solar farm, approved on 28 June 2024, not yet built), 7.0 km away. Offshore, 2 wind farms are recorded within 40 km; the nearest is Kentish Flats 2 (49.5 MW, operational), 34.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of ME8
Projects of 1 MW and more (12)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Phinia, Courteney Roadrooftop solar | rooftop solar | 1.8 | approved, not builtupdated Feb 2025 | Dec 2023 | granted Mar 2024 | Feb 2025 | Medway | 1.1 |
| Iwade Solar Farmsolar farm | solar farm | 1.7 | operationalupdated Nov 2016 | Jan 2013 | granted Jul 2013 | Nov 2016 | Swale | 4.0 |
| Mid Kent College Medway Campus, Medway Road Battery Storage, ASHPbattery storage | battery storage | 1 | approved, not builtupdated Feb 2024 | Nov 2023 | granted Nov 2023 | Feb 2024 | Medway | 5.3 |
| Bobbing solar farmsolar farm | solar farm | 11.3 | operationalupdated Apr 2016 | May 2014 | granted Dec 2015 | Apr 2016 | Swale | 6.4 |
| Harp Farm Solar Parksolar farm | solar farm | 15 | refusedupdated Jun 2026 | Jun 2025 | refused Apr 2026 | Jun 2026 | Maidstone | 6.8 |
| Raspberrysolar farm | solar farm | 49.9 | approved, not builtupdated Jun 2026 | Jun 2022 | granted Jun 2024 | Jun 2026 | Swale | 7.0 |
| Orchard Farmsolar farm | solar farm | 10 | operationalupdated Mar 2016 | Aug 2014 | granted Oct 2014 | Mar 2016 | Swale | 7.1 |
| Vigo Lane, Borden Solar Farmsolar farm | solar farm | 40 | approved, not builtupdated Sep 2025 | May 2023 | granted Sep 2025 | Sep 2025 | Swale | 7.8 |
| London Medway Commercial Parkrooftop solar | rooftop solar | 1.3 | approved, not built may be out of dateupdated Dec 2021 | Jan 2021 | granted May 2021 | Dec 2021 | Medway | 8.2 |
| Biossence Solar Parksolar farm | solar farm | 4.5 | operationalupdated Mar 2013 | Apr 2011 | granted Jun 2011 | Mar 2013 | Tonbridge and Malling | 9.3 |
| Sundridge Hillbattery storage | battery storage | 49.5 | under constructionupdated Mar 2022 | Nov 2017 | granted Aug 2018 | Mar 2022 | Medway | 9.3 |
| Wouldham Road, Wouldhambattery storage | battery storage | 7.5 | approved, not built may be out of dateupdated Dec 2021 | Nov 2021 | granted Jan 2022 | Dec 2021 | Tonbridge and Malling | 9.4 |
Smaller schemes under 1 MW, mostly rooftop solar (15)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Gillingham Technical Centre, Courteney Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Feb 2025 | Feb 2024 | granted Apr 2024 | Feb 2025 | Medway | 1.1 |
| Gillingham Technical Centre, Phinia Courteney Road Solar PV Systemsrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Apr 2024 | Mar 2024 | granted Apr 2024 | Apr 2024 | Medway | 1.2 |
| Cloverlay Industrial Park, Canterbury Lane - Micro Energy Storage Systembattery storage | battery storage | 0.2 | application withdrawnupdated Apr 2026 | Dec 2025 | — | Apr 2026 | Medway | 2.2 |
| Beechings Way, Eastcourt Lanebattery storage | battery storage | — | approved, not builtupdated Sep 2025 | Jul 2025 | granted Sep 2025 | Sep 2025 | Medway | 2.3 |
| Featherby Road, Bredgar Road - Micro Energy Storagebattery storage | battery storage | 0.2 | refusedupdated Mar 2026 | Dec 2025 | refused Feb 2026 | Mar 2026 | Medway | 2.5 |
| Burnt Oak Primary School, Richmond Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Mar 2026 | Nov 2025 | granted Jan 2026 | Mar 2026 | Medway | 4.7 |
| Mill Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Dec 2021 | Dec 2021 | granted Mar 2022 | Dec 2021 | Medway | 5.1 |
| Mid Kent College, Medway Roadrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Aug 2023 | Aug 2023 | granted Sep 2023 | Aug 2023 | Medway | 5.3 |
| Maritime Way, Gillinghamrooftop solar | rooftop solar | — | refusedupdated Mar 2022 | Feb 2022 | refused May 2022 | Mar 2022 | Medway | 6.2 |
| Medway One Energy Hubbattery storage | battery storage | — | approved, not built may be out of dateupdated Jul 2024 | Mar 2024 | granted Jul 2024 | Jul 2024 | Medway | 6.3 |
| Event Centre, Detling Hillrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jun 2026 | Mar 2026 | granted May 2026 | Jun 2026 | Maidstone | 6.8 |
| Raspberrybattery storage | battery storage | — | approved, not builtupdated Jun 2026 | Jun 2022 | granted Jun 2024 | Jun 2026 | Swale | 7.0 |
| Morrisons Supermarket, Rochesterrooftop solar | rooftop solar | — | approved, not builtupdated Apr 2022 | Mar 2022 | granted May 2022 | Apr 2022 | Medway | 8.0 |
| Four Elms Roundabout, Wainscott - Micro Energy Storagebattery storage | battery storage | 0.2 | approved, not builtupdated Sep 2025 | Jul 2025 | granted Sep 2025 | Sep 2025 | Medway | 8.2 |
| Mackenders Close - Micro Energy Storage Facilitybattery storage | battery storage | 0.2 | approved, not builtupdated Mar 2025 | Oct 2024 | granted Jan 2025 | Mar 2025 | Tonbridge and Malling | 9.5 |
Distance from the average position of the ME8 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 7 | 0 | 2 | 4 | 1 | 89.9 |
| Rooftop solar | 10 | 0 | 9 | 0 | 1 | 4.8 |
| Battery storage | 10 | 0 | 8 | 0 | 1 | 58.4 |
MW in pipeline: pending, approved and under-construction capacity.
Offshore wind farms within 40 km
| Wind farm | MW | Status (REPD) | km |
|---|---|---|---|
| Kentish Flats 2 | 49.5 | operationalupdated Jun 2016 | 34.9 |
| Kentish Flats | 90 | operationalupdated Oct 2017 | 36.1 |
Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.
How Medway decides solar, wind and battery applications
| Applications | Medway | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 18 | 10,236 |
| Refused | 3 (17%) | 19% |
| Solar refused | 1 of 10 | 12% |
| Onshore wind refused | 1 of 1 | 45% |
| Battery storage refused | 1 of 7 | 16% |
| Median time from submission to decision | 10.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 0 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near ME8, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.