Solar, wind and battery projects near Rochester (ME2)
27 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of ME2 (Medway): 2 are waiting for a planning decision, 18 approved but not yet running, 3 operational. The largest live scheme is Sundridge Hill (49.5 MW battery storage, under construction since 1 February 2022), 2.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of ME2
Projects of 1 MW and more (9)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Sundridge Hillbattery storage | battery storage | 49.5 | under constructionupdated Mar 2022 | Nov 2017 | granted Aug 2018 | Mar 2022 | Medway | 2.0 |
| Mid Kent College Medway Campus, Medway Road Battery Storage, ASHPbattery storage | battery storage | 1 | approved, not builtupdated Feb 2024 | Nov 2023 | granted Nov 2023 | Feb 2024 | Medway | 4.2 |
| Wouldham Road, Wouldhambattery storage | battery storage | 7.5 | approved, not built may be out of dateupdated Dec 2021 | Nov 2021 | granted Jan 2022 | Dec 2021 | Tonbridge and Malling | 4.6 |
| Phinia, Courteney Roadrooftop solar | rooftop solar | 1.8 | approved, not builtupdated Feb 2025 | Dec 2023 | granted Mar 2024 | Feb 2025 | Medway | 7.8 |
| Biossence Solar Parksolar farm | solar farm | 4.5 | operationalupdated Mar 2013 | Apr 2011 | granted Jun 2011 | Mar 2013 | Tonbridge and Malling | 7.9 |
| Aylesford BESSbattery storage | battery storage | 29 | operationalupdated Mar 2026 | Sep 2017 | granted Dec 2017 | Mar 2026 | Tonbridge and Malling | 8.6 |
| Tilbury Energy Centrebattery storage | battery storage | 100 | abandonedupdated Jan 2020 | Feb 2018 | — | Jan 2020 | Thurrock | 8.7 |
| Barvills Solar Farmsolar farm | solar farm | 5 | operationalupdated Oct 2017 | Mar 2015 | granted Aug 2015 | Oct 2017 | Thurrock | 9.8 |
| Harp Farm Solar Parksolar farm | solar farm | 15 | refusedupdated Jun 2026 | Jun 2025 | refused Apr 2026 | Jun 2026 | Maidstone | 10.0 |
Smaller schemes under 1 MW, mostly rooftop solar (18)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Morrisons Supermarket, Rochesterrooftop solar | rooftop solar | — | approved, not builtupdated Apr 2022 | Mar 2022 | granted May 2022 | Apr 2022 | Medway | 0.8 |
| Four Elms Roundabout, Wainscott - Micro Energy Storagebattery storage | battery storage | 0.2 | approved, not builtupdated Sep 2025 | Jul 2025 | granted Sep 2025 | Sep 2025 | Medway | 3.4 |
| Maritime Way, Gillinghamrooftop solar | rooftop solar | — | refusedupdated Mar 2022 | Feb 2022 | refused May 2022 | Mar 2022 | Medway | 3.8 |
| Mill Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Dec 2021 | Dec 2021 | granted Mar 2022 | Dec 2021 | Medway | 4.1 |
| Mid Kent College, Medway Roadrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Aug 2023 | Aug 2023 | granted Sep 2023 | Aug 2023 | Medway | 4.2 |
| Burnt Oak Primary School, Richmond Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Mar 2026 | Nov 2025 | granted Jan 2026 | Mar 2026 | Medway | 4.8 |
| Featherby Road, Bredgar Road - Micro Energy Storagebattery storage | battery storage | 0.2 | refusedupdated Mar 2026 | Dec 2025 | refused Feb 2026 | Mar 2026 | Medway | 6.9 |
| Beechings Way, Eastcourt Lanebattery storage | battery storage | — | approved, not builtupdated Sep 2025 | Jul 2025 | granted Sep 2025 | Sep 2025 | Medway | 7.0 |
| Gillingham Technical Centre, Phinia Courteney Road Solar PV Systemsrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Apr 2024 | Mar 2024 | granted Apr 2024 | Apr 2024 | Medway | 7.6 |
| Gillingham Technical Centre, Courteney Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Feb 2025 | Feb 2024 | granted Apr 2024 | Feb 2025 | Medway | 7.8 |
| Lion Business Park, Dering Wayrooftop solar | rooftop solar | 0.2 | application submitted may be out of dateupdated Apr 2024 | Mar 2024 | — | Apr 2024 | Gravesham | 7.9 |
| Mackenders Close - Micro Energy Storage Facilitybattery storage | battery storage | 0.2 | approved, not builtupdated Mar 2025 | Oct 2024 | granted Jan 2025 | Mar 2025 | Tonbridge and Malling | 8.3 |
| Corona Terrace And Hollow Lane - Micro Energy Storage Systembattery storage | battery storage | 0.2 | application submittedupdated Dec 2025 | Nov 2025 | — | Dec 2025 | Tonbridge and Malling | 8.5 |
| Unit A Riverside Business Parkrooftop solar | rooftop solar | 1 | approved, not builtupdated May 2022 | May 2022 | granted Jul 2022 | May 2022 | Tonbridge and Malling | 8.6 |
| Corona Terrace & Hollow Lane - Micro Energy Storagebattery storage | battery storage | 0.2 | approved, not builtupdated Jun 2026 | Nov 2025 | granted May 2026 | Jun 2026 | Tonbridge and Malling | 8.7 |
| Medway One Energy Hubbattery storage | battery storage | — | approved, not built may be out of dateupdated Jul 2024 | Mar 2024 | granted Jul 2024 | Jul 2024 | Medway | 8.7 |
| Morrisons, Coldharbour Road Solar Photovoltaics Panelsrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Dec 2022 | Oct 2022 | granted Dec 2022 | Dec 2022 | Gravesham | 9.4 |
| Larkfield Leisure Centre, New Hythe Lanerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jan 2025 | Oct 2024 | granted Dec 2024 | Jan 2025 | Tonbridge and Malling | 9.6 |
Distance from the average position of the ME2 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 3 | 0 | 0 | 2 | 1 | 0 |
| Rooftop solar | 12 | 1 | 10 | 0 | 1 | 4.9 |
| Battery storage | 12 | 1 | 8 | 1 | 1 | 58.8 |
MW in pipeline: pending, approved and under-construction capacity.
How Medway decides solar, wind and battery applications
| Applications | Medway | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 18 | 10,236 |
| Refused | 3 (17%) | 19% |
| Solar refused | 1 of 10 | 12% |
| Onshore wind refused | 1 of 1 | 45% |
| Battery storage refused | 1 of 7 | 16% |
| Median time from submission to decision | 10.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 0 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near ME2, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.