Energy Projects Near You

Renewable energy projects in Medway

19 solar, wind or battery projects of 150 kW or more are located in Medway (REPD, July 2026 extract): 0 pending, 14 approved but not running, 1 operational and 3 refused. The council refused 3 of 18 decided applications (17%; UK 19%), with a median 10 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

19projects in the council area
0awaiting a decision
14approved, not running
17%of decisions refused

How Medway decides

ApplicationsMedwayUK
Decided applications (solar, wind, battery)1810,236
Refused3 (17%)19%
Solar refused1 of 1012%
Onshore wind refused1 of 145%
Battery storage refused1 of 716%
Median time from submission to decision10.3 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Projects in Medway

Projects of 1 MW and more (7)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Power Station Road, Isle Of Grainbattery storagebattery storage249approved, not builtupdated Jan 2026Jul 2025granted Dec 2025Jan 2026
Sundridge Hillbattery storagebattery storage49.5under constructionupdated Mar 2022Nov 2017granted Aug 2018Mar 2022
Malmaynes Hall Farmsolar farmsolar farm12operationalupdated Jun 2015Jul 2014granted Nov 2014Jun 2015
Perry's Farm Wind Farmwind farmwind farm6.8refusedupdated May 2016Jun 2015refused Jan 2016May 2016
Phinia, Courteney Roadrooftop solarrooftop solar1.8approved, not builtupdated Feb 2025Dec 2023granted Mar 2024Feb 2025
London Medway Commercial Parkrooftop solarrooftop solar1.3approved, not built may be out of dateupdated Dec 2021Jan 2021granted May 2021Dec 2021
Mid Kent College Medway Campus, Medway Road Battery Storage, ASHPbattery storagebattery storage1approved, not builtupdated Feb 2024Nov 2023granted Nov 2023Feb 2024
Smaller schemes under 1 MW, mostly rooftop solar (12)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Mid Kent College, Medway Roadrooftop solarrooftop solar0.4approved, not builtupdated Aug 2023Aug 2023granted Sep 2023Aug 2023
Gillingham Technical Centre, Phinia Courteney Road Solar PV Systemsrooftop solarrooftop solar0.3approved, not builtupdated Apr 2024Mar 2024granted Apr 2024Apr 2024
Gillingham Technical Centre, Courteney Roadrooftop solarrooftop solar0.3approved, not builtupdated Feb 2025Feb 2024granted Apr 2024Feb 2025
Mill Roadrooftop solarrooftop solar0.3approved, not builtupdated Dec 2021Dec 2021granted Mar 2022Dec 2021
Four Elms Roundabout, Wainscott - Micro Energy Storagebattery storagebattery storage0.2approved, not builtupdated Sep 2025Jul 2025granted Sep 2025Sep 2025
Featherby Road, Bredgar Road - Micro Energy Storagebattery storagebattery storage0.2refusedupdated Mar 2026Dec 2025refused Feb 2026Mar 2026
Cloverlay Industrial Park, Canterbury Lane - Micro Energy Storage Systembattery storagebattery storage0.2application withdrawnupdated Apr 2026Dec 2025—Apr 2026
Burnt Oak Primary School, Richmond Roadrooftop solarrooftop solar0.2approved, not builtupdated Mar 2026Nov 2025granted Jan 2026Mar 2026
Maritime Way, Gillinghamrooftop solarrooftop solar—refusedupdated Mar 2022Feb 2022refused May 2022Mar 2022
Morrisons Supermarket, Rochesterrooftop solarrooftop solar—approved, not builtupdated Apr 2022Mar 2022granted May 2022Apr 2022
Medway One Energy Hubbattery storagebattery storage—approved, not built may be out of dateupdated Jul 2024Mar 2024granted Jul 2024Jul 2024
Beechings Way, Eastcourt Lanebattery storagebattery storage—approved, not builtupdated Sep 2025Jul 2025granted Sep 2025Sep 2025

Postcode districts in Medway

DistrictProjects within 10 kmPendingApprovedOperational
ME1272192
ME2272183
ME3220152
ME4261183
ME5313203
ME7290196
ME8270194

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Medway by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.