Energy Projects Near You

Sundridge Hill (49.5 MW battery storage)

Sundridge Hill is a 49.5 MW battery storage project in Medway, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 February 2022; the record was last updated on 17 March 2022.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.5 MWbattery storage
under constructionstatus in REPD
17 March 2022record last updated
Medwaycouncil area

Planning timeline

DateStage
14 November 2017Application submitted
17 August 2018Planning permission granted
1 February 2022Construction started

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.5 MW
Status (REPD)
under construction
Record last updated
17 March 2022
Operator or applicant
RNA Energy
Planning authority
Medway
Planning application reference
MC/17/3770
Address (REPD)
Land To South Of A228, Sundridge Hill, Cuxton, Rochester,
Council area (by location)
Medway
Time to decision
39 weeks
REPD reference
7081

Who decides

ApplicationsMedwayUK
Decided applications (solar, wind, battery)1810,236
Refused3 (17%)19%
Solar refused1 of 1012%
Onshore wind refused1 of 145%
Battery storage refused1 of 716%
Median time from submission to decision10.3 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Wouldham Road, Wouldhambattery storage7.5approved, not built2.7
Aylesford BESSbattery storage29operational6.8
Harp Farm Solar Parksolar farm15refused9.1
Idleigh Court Road, New Ash Greensolar farm49.9application submitted9.6
Tilbury Energy Centrebattery storage100abandoned9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.3765, 0.465).