Energy Projects Near You

Malmaynes Hall Farm (12 MW solar farm)

Malmaynes Hall Farm is a 12 MW solar farm project in Medway, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2015; the record was last updated on 19 June 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12 MWsolar farm
operationalstatus in REPD
19 June 2015record last updated
Medwaycouncil area

Planning timeline

DateStage
31 July 2014Application submitted
6 November 2014Planning permission granted
15 November 2014Construction started
31 March 2015Operational

Project details

Technology
solar farm
Capacity
12 MW
Status (REPD)
operational
Record last updated
19 June 2015
Operator or applicant
Wessex Solar Energy
Planning authority
Medway
Planning application reference
MC/14/2082
Site area
26.6 ha
Address (REPD)
LAND OFF MALMAYNES HALL FARM, MALMAYNES HALL ROAD, STOKE, ROCHESTER, KENT
Council area (by location)
Medway
Time to decision
14 weeks
Name in REPD
MALMAYNES HALL FARM
REPD reference
2135

Who decides

ApplicationsMedwayUK
Decided applications (solar, wind, battery)1810,236
Refused3 (17%)19%
Solar refused1 of 1012%
Onshore wind refused1 of 145%
Battery storage refused1 of 716%
Median time from submission to decision10.3 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Perry's Farm Wind Farmwind farm6.8refused4.5
Power Station Road, Isle Of Grainbattery storage249approved, not built7.0
Port of Sheerness Wind Farm (was Lappel Bank)wind farm8.2operational9.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.4551, 0.6142).