Barvills Solar Farm (5 MW)

Barvills Solar Farm is a 5 MW solar farm project in Thurrock, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 29 March 2017; the record was last updated on 4 October 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
4 October 2017record last updated
Thurrockcouncil area

Planning timeline

DateStage
19 March 2015Application submitted
7 August 2015Planning permission granted
29 January 2017Construction started
29 March 2017Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
4 October 2017
Operator or applicant
BE Renewables/Barvills Solar Limited
Planning authority
Thurrock
Planning application reference
15/00288/FUL
Site area
6.8 ha
Address (REPD)
Barvills Farm, Princess Margaret Road, East Tilbury, Thurrock
Council area (by location)
Thurrock
Time to decision
20 weeks
REPD reference
5942

Earlier applications for this site

ApplicationMWSubmittedOutcome
Barvills Solar Farm 14/01124/FUL11.621 October 2014withdrawn 16 March 2015

Who decides

ApplicationsThurrockUK
Decided applications (solar, wind, battery)2810,236
Refused3 (11%)19%
Solar refused2 of 1812%
Onshore wind refused0 of 245%
Battery storage refused1 of 816%
Median time from submission to decision20.3 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Tilbury Energy Centrebattery storage100abandoned1.2
Thurrock Flexible Generation Plantbattery storage150operational3.2
The Place Solar Farmsolar farm23.2refused4.2
Tilbury Dockswind farm12operational6.2
Gateway Energy Centrebattery storage450approved, not built6.5
Marsh Farm, Fobbing Solar Arrays & Battery Storagesolar farm49.9application withdrawn7.2
Thames Way, Northfleetbattery storage100application submitted7.4
Land adjacent to the former Coryton Refinerysolar farm5abandoned8.2
Foxhounds Lane, Southfleetbattery storage300refused9.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.4721, 0.4234).