Solar, wind and battery projects near Stanford-le-Hope (SS17)
44 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SS17 (Thurrock): 5 are waiting for a planning decision, 17 approved but not yet running, 14 operational. The largest live scheme is Gateway Energy Centre (450 MW battery storage, approved on 13 January 2023, not yet built), 4.1 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of SS17
Projects of 1 MW and more (25)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Marsh Farm, Fobbing Solar Arrays & Battery Storagesolar farm | solar farm | 49.9 | application withdrawnupdated Jun 2024 | Jul 2023 | — | Jun 2024 | Thurrock | 2.7 |
| Gateway Energy Centrebattery storage | battery storage | 450 | approved, not builtupdated Dec 2021 | Nov 2021 | granted Jan 2023 | Dec 2021 | Thurrock | 4.1 |
| Land adjacent to the former Coryton Refinerysolar farm | solar farm | 5 | abandonedupdated Nov 2017 | Sep 2015 | granted Feb 2016 | Nov 2017 | Thurrock | 4.9 |
| Lime Kilns Energy Centrebattery storage | battery storage | 6 | approved, not builtupdated Jul 2025 | Oct 2024 | granted Dec 2024 | Jul 2025 | Thurrock | 5.0 |
| Barvills Solar Farmsolar farm | solar farm | 5 | operationalupdated Oct 2017 | Mar 2015 | granted Aug 2015 | Oct 2017 | Thurrock | 5.6 |
| Fairwind Farmsolar farm | solar farm | 10 | operationalupdated Jul 2015 | Jun 2013 | granted Nov 2013 | Jul 2015 | Basildon | 5.8 |
| Lower Dunton Roadbattery storage | battery storage | 368 | application submittedupdated Nov 2024 | Oct 2024 | — | Nov 2024 | Basildon | 5.9 |
| Lower Dunton Road Battery Storage Facilitybattery storage | battery storage | 28 | operationalupdated Feb 2026 | Oct 2020 | granted Feb 2021 | Feb 2026 | Basildon | 5.9 |
| Tilbury Energy Centrebattery storage | battery storage | 100 | abandonedupdated Jan 2020 | Feb 2018 | — | Jan 2020 | Thurrock | 6.7 |
| Ford Research And Engineering Centre, Dunton Solar Farmsolar farm | solar farm | 5.2 | operationalupdated Mar 2025 | Jun 2022 | granted Feb 2023 | Mar 2025 | Basildon | 7.0 |
| Bulphan Fen Solar Farm & Battery Storagesolar farm | solar farm | 49.9 | under constructionupdated Jul 2025 | Jan 2021 | granted Oct 2021 | Jul 2025 | Thurrock | 7.1 |
| The Place Solar Farmsolar farm | solar farm | 23.2 | refusedupdated Nov 2016 | Dec 2014 | refused Nov 2016 | Nov 2016 | Thurrock | 7.3 |
| Thurrock Flexible Generation Plantbattery storage | battery storage | 150 | operationalupdated Aug 2025 | Jun 2020 | granted Feb 2022 | Aug 2025 | Thurrock | 8.1 |
| Whites Farmbattery storage | battery storage | 49.9 | refusedupdated Aug 2023 | Jul 2022 | refused Jul 2023 | Aug 2023 | Basildon | 8.2 |
| Ockendon Landfill Solar Farmsolar farm | solar farm | 38 | operationalupdated Sep 2023 | Jul 2014 | granted Jan 2016 | Sep 2023 | Thurrock | 8.3 |
| Clay Tye Road Solar Farmsolar farm | solar farm | 49.9 | application submitted may be out of dateupdated May 2021 | Apr 2021 | — | May 2021 | Thurrock | 8.3 |
| Fen Lane, Bulphan Solar Farmsolar farm | solar farm | 49.9 | under constructionupdated Mar 2024 | Jan 2021 | granted Jul 2021 | Mar 2024 | Havering | 8.3 |
| Tilbury LCY2rooftop solar | rooftop solar | 4 | operationalupdated Feb 2020 | Aug 2018 | — | Feb 2020 | Thurrock | 8.4 |
| London Distribution Parkbattery storage | battery storage | 3.8 | operationalupdated Oct 2022 | Aug 2018 | — | Oct 2022 | Thurrock | 8.4 |
| Crouch Solar Farmsolar farm | solar farm | 49.9 | operationalupdated Oct 2024 | May 2021 | granted Dec 2021 | Oct 2024 | Brentwood | 8.7 |
| Crouch Solar Farmbattery storage | battery storage | 49.9 | operationalupdated Oct 2024 | May 2021 | granted Dec 2021 | Oct 2024 | Brentwood | 8.7 |
| Barleylands Solar Farmsolar farm | solar farm | 17 | approved, not builtupdated Oct 2024 | Nov 2023 | granted Oct 2024 | Oct 2024 | Basildon | 8.8 |
| Nevendonbattery storage | battery storage | 10 | operationalupdated Mar 2017 | — | — | Mar 2017 | Basildon | 8.9 |
| Nevendon Battery Storage Extensionbattery storage | battery storage | 5 | operationalupdated Feb 2025 | Jan 2023 | granted May 2023 | Feb 2025 | Basildon | 8.9 |
| Crays Hall Farm Solar Arrayssolar farm | solar farm | 25.6 | operationalupdated Jun 2026 | Mar 2022 | granted Aug 2023 | Jun 2026 | Basildon | 10.0 |
Smaller schemes under 1 MW, mostly rooftop solar (19)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Marsh Farm, Fobbing Solar Arrays & Battery Storagebattery storage | battery storage | — | application withdrawnupdated Jun 2024 | Jul 2023 | — | Jun 2024 | Thurrock | 2.7 |
| Ambrose Close & Gloucester Park, Broadmaynebattery storage | battery storage | 0.2 | application withdrawnupdated Dec 2025 | Feb 2025 | — | Dec 2025 | Basildon | 5.7 |
| Tesco Extra, Hazelmerebattery storage | battery storage | 0.2 | approved, not builtupdated May 2025 | Jan 2025 | granted Apr 2025 | May 2025 | Basildon | 6.3 |
| Tesco Extra Hazelmererooftop solar | rooftop solar | 0.4 | operationalupdated Oct 2019 | Jan 2019 | granted Mar 2019 | Oct 2019 | Basildon | 6.3 |
| Miles Gray Road, Steeple View - Micro Energy Storagebattery storage | battery storage | 0.2 | approved, not builtupdated May 2026 | Jan 2026 | granted Mar 2026 | May 2026 | Basildon | 7.0 |
| Bulphan Fen Solar Farm & Battery Storagebattery storage | battery storage | — | under constructionupdated Jul 2025 | Jan 2021 | granted Oct 2021 | Jul 2025 | Thurrock | 7.1 |
| David Lloyd Leisure, Festival Way - Soalr Panelsrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Feb 2024 | Dec 2023 | granted Feb 2024 | Feb 2024 | Basildon | 7.4 |
| Whitmore Way - Micro Energy Storage Projectbattery storage | battery storage | 0.2 | application withdrawnupdated Dec 2025 | Feb 2025 | — | Dec 2025 | Basildon | 7.4 |
| Morrisons PV Solar Panelsrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Feb 2022 | Feb 2022 | granted Mar 2022 | Feb 2022 | Castle Point | 7.8 |
| Endeavour Point, Endeavour Driverooftop solar | rooftop solar | 0.5 | application submittedupdated Jan 2025 | Nov 2024 | — | Jan 2025 | Basildon | 7.9 |
| Phoenix House, Christopher Martin Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jan 2023 | Nov 2022 | granted Dec 2022 | Jan 2023 | Basildon | 8.7 |
| J Sainsbury, Cricketers Wayrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Apr 2025 | Feb 2025 | granted Mar 2025 | Apr 2025 | Basildon | 8.8 |
| Barleylands Solar Farmbattery storage | battery storage | — | approved, not builtupdated Oct 2024 | Nov 2023 | granted Oct 2024 | Oct 2024 | Basildon | 8.8 |
| Unit 1, Watkins Closerooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jul 2023 | May 2023 | granted Jul 2023 | Jul 2023 | Basildon | 9.1 |
| Tilbury Green Power Stationrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Mar 2025 | Dec 2024 | granted Feb 2025 | Mar 2025 | Thurrock | 9.3 |
| Burnt Mills Industrial Estate, Hovefields Avenuebattery storage | battery storage | 0.2 | approved, not builtupdated May 2026 | Dec 2025 | granted Mar 2026 | May 2026 | Basildon | 9.3 |
| Morrisonsrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Mar 2022 | Feb 2022 | granted Apr 2022 | Mar 2022 | Thurrock | 9.5 |
| Sewage Pumping Station, Rushbottom Lane - Micro Energy Storagebattery storage | battery storage | 0.2 | application submittedupdated Aug 2025 | Jul 2025 | — | Aug 2025 | Castle Point | 9.6 |
| Lion Business Park, Dering Wayrooftop solar | rooftop solar | 0.2 | application submitted may be out of dateupdated Apr 2024 | Mar 2024 | — | Apr 2024 | Gravesham | 9.7 |
Distance from the average position of the SS17 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 13 | 1 | 3 | 6 | 1 | 167 |
| Rooftop solar | 11 | 2 | 7 | 2 | 0 | 3.3 |
| Battery storage | 20 | 2 | 7 | 6 | 1 | 825 |
MW in pipeline: pending, approved and under-construction capacity.
How Thurrock decides solar, wind and battery applications
| Applications | Thurrock | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 28 | 10,236 |
| Refused | 3 (11%) | 19% |
| Solar refused | 2 of 18 | 12% |
| Onshore wind refused | 0 of 2 | 45% |
| Battery storage refused | 1 of 8 | 16% |
| Median time from submission to decision | 20.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 0 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near SS17, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.