Energy Projects Near You

Bulphan Fen Solar Farm & Battery Storage (49.9 MW)

Bulphan Fen Solar Farm & Battery Storage is a 49.9 MW solar farm project in Thurrock, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 March 2025; the record was last updated on 28 July 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
under constructionstatus in REPD
28 July 2025record last updated
Thurrockcouncil area

Planning timeline

DateStage
18 January 2021Application submitted
21 October 2021Planning permission granted
1 March 2025Construction started

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
under construction
Record last updated
28 July 2025
Operator or applicant
Warley Green Limited
Planning authority
Thurrock
Planning application reference
21/00077/FUL
Site area
168.0 ha
Address (REPD)
Land Adjacent Fen Farm Judds Farm And Part Of Bulphan Fen Harrow Lane Bulphan
Council area (by location)
Thurrock
Time to decision
39 weeks
REPD reference
8026

The scheme also includes battery storage, recorded separately in REPD (under construction).

Who decides

ApplicationsThurrockUK
Decided applications (solar, wind, battery)2810,236
Refused3 (11%)19%
Solar refused2 of 1812%
Onshore wind refused0 of 245%
Battery storage refused1 of 816%
Median time from submission to decision20.3 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Clay Tye Road Solar Farmsolar farm49.9application submitted1.2
Fen Lane, Bulphan Solar Farmsolar farm49.9under construction1.3
Ockendon Landfill Solar Farmsolar farm38operational2.0
Clay Tye Farmsolar farm15.9refused3.1
Clay Tye Farm Phase 2 - Storage Facilitybattery storage49.5operational3.4
Clay Tye Farm Phase 1 - Storage Facilitybattery storage49.5operational3.4
Clay Tye Farm Energy Storage Facilitybattery storage200application submitted3.4
Lime Kilns Energy Centrebattery storage6approved, not built4.2
Fairwind Farmsolar farm10operational4.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.5392, 0.3399).