Ockendon Landfill Solar Farm (38 MW)

Ockendon Landfill Solar Farm is a 38 MW solar farm project in Thurrock, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 September 2023; the record was last updated on 14 September 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

38 MWsolar farm
operationalstatus in REPD
14 September 2023record last updated
Thurrockcouncil area

Planning timeline

DateStage
29 July 2014Application submitted
22 January 2016Planning permission granted
1 September 2022Construction started
1 September 2023Operational

Project details

Technology
solar farm
Capacity
38 MW
Status (REPD)
operational
Record last updated
14 September 2023
Operator or applicant
NTR Plc
Planning authority
Thurrock
Planning application reference
14/00836/FUL
Site area
98.4 ha
Address (REPD)
South Ockendon Quarry And Landfill Site Medebridge Road South Ockendon Essex
Council area (by location)
Thurrock
Time to decision
77 weeks
REPD reference
2053

Who decides

ApplicationsThurrockUK
Decided applications (solar, wind, battery)2810,236
Refused3 (11%)19%
Solar refused2 of 1812%
Onshore wind refused0 of 245%
Battery storage refused1 of 816%
Median time from submission to decision20.3 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Clay Tye Road Solar Farmsolar farm49.9application submitted1.6
Fen Lane, Bulphan Solar Farmsolar farm49.9under construction1.7
Bulphan Fen Solar Farm & Battery Storagesolar farm49.9under construction2.0
Medebridge Road Solar Farmsolar farm49.9operational2.6
Clay Tye Farm Phase 1 - Storage Facilitybattery storage49.5operational3.3
Clay Tye Farm Phase 2 - Storage Facilitybattery storage49.5operational3.3
Clay Tye Farm Energy Storage Facilitybattery storage200application submitted3.3
Clay Tye Farmsolar farm15.9refused3.6
Lime Kilns Energy Centrebattery storage6approved, not built6.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.5262, 0.3191).