Energy Projects Near You

Solar, wind and battery projects near Purfleet (RM19)

76 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of RM19 (Thurrock): 5 are waiting for a planning decision, 46 approved but not yet running, 15 operational. The largest live scheme is Manor Farm, Dartford Road (212 MW battery storage, application submitted on 5 June 2025, no decision recorded), 7.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

76projects within 10 km
5awaiting a decision
46approved, not running
15operational

Projects within 10 km of RM19

Projects of 1 MW and more (40)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Ocado Operating Limited, New Purfleet Roadrooftop solarrooftop solar2.8approved, not builtupdated May 2025Mar 2025granted May 2025May 2025Thurrock1.7
Tesco, Cygnet View Solar PV Arraysrooftop solarrooftop solar1.1approved, not builtupdated Apr 2026Jan 2026granted Mar 2026Apr 2026Thurrock2.3
Aveley Landfill, Sandy Lane PV Solar Array & Battery Energy Storagesolar farmsolar farm16approved, not builtupdated Feb 2025Feb 2024granted Jul 2024Feb 2025Thurrock2.3
Littlebrook Battery Storagebattery storagebattery storage7.5operationalupdated Feb 2026Jul 2016granted Sep 2016Feb 2026Dartford2.6
Albion Roadbattery storagebattery storage5application withdrawnupdated Jun 2020Jul 2019—Jun 2020Dartford2.7
Intu Lakeside, West Thurrock Wayrooftop solarrooftop solar1.3approved, not builtupdated Sep 2024Jul 2024granted Sep 2024Sep 2024Thurrock2.7
Land Adjacent Davanden Kennelsbattery storagebattery storage7.5abandonedupdated Feb 2020May 2018—Feb 2020Dartford3.6
Neatscourtbattery storagebattery storage1abandonedupdated Jun 2020Jun 2017—Jun 2020Dartford4.0
Medebridge Road Solar Farmsolar farmsolar farm49.9operationalupdated Nov 2025Feb 2022granted May 2022Nov 2025Thurrock4.5
Bean Lanebattery storagebattery storage104application withdrawnupdated Jan 2026Apr 2025—Jan 2026Dartford4.9
Little Belhus Restoration Sitewind farmwind farm1operationalupdated Jan 2017Nov 2013granted May 2015Jan 2017Thurrock5.0
Bluewater Shopping Centre, Upper Thames Walk Solar Photovoltaic Panelrooftop solarrooftop solar1.3approved, not built may be out of dateupdated Apr 2023Jan 2023granted Apr 2023Apr 2023Dartford5.2
Darenth Roadbattery storagebattery storage99.9approved, not builtupdated Oct 2025May 2025granted Oct 2025Oct 2025Dartford5.7
Riverside Resource Recovery Facility Battery Storagebattery storagebattery storage2.5under constructionupdated Jan 2021Dec 2020—Jan 2021Bexley6.7
Riverside Energy Parkbattery storagebattery storage20approved, not built may be out of dateupdated Apr 2022Nov 2018granted Apr 2020Apr 2022Bexley6.8
Riverside Energy Park (REP)rooftop solarrooftop solar1approved, not built may be out of dateupdated Sep 2020Nov 2018granted Apr 2020Sep 2020Bexley6.8
Tilbury Dockswind farmwind farm12operationalupdated Jul 2017Dec 2007granted May 2008Jul 2017Thurrock7.0
Ockendon Landfill Solar Farmsolar farmsolar farm38operationalupdated Sep 2023Jul 2014granted Jan 2016Sep 2023Thurrock7.1
Crossness Sewage Works Turbinewind turbinewind turbine2.5operationalupdated Jan 2015Nov 2010granted Dec 2010Jan 2015Bexley7.4
Ford Wind Park - Dagenhamwind farmwind farm5.9operationalupdated Aug 2011Mar 2003granted Jul 2003Aug 2011Barking and Dagenham7.6
Tilbury LCY2rooftop solarrooftop solar4operationalupdated Feb 2020Aug 2018—Feb 2020Thurrock7.7
London Distribution Parkbattery storagebattery storage3.8operationalupdated Oct 2022Aug 2018—Oct 2022Thurrock7.7
Manor Farm, Dartford Roadbattery storagebattery storage212application submittedupdated Jul 2025Jun 2025—Jul 2025Bexley7.9
Crossness Sewage Works PVrooftop solarrooftop solar1.5operationalupdated Jan 2012——Jan 2012Bexley7.9
Thames Way, Northfleetbattery storagebattery storage100application submittedupdated Sep 2025Aug 2025—Sep 2025Gravesham8.0
Ford Motor Company Ltd (Extension)wind turbinewind turbine2operationalupdated Sep 2011Apr 2009granted Jul 2009Sep 2011Barking and Dagenham8.3
The Place Solar Farmsolar farmsolar farm23.2refusedupdated Nov 2016Dec 2014refused Nov 2016Nov 2016Thurrock8.3
New Barn Roadbattery storagebattery storage35approved, not builtupdated Feb 2024Aug 2023granted Feb 2024Feb 2024Dartford8.3
Dartford BESSbattery storagebattery storage300application withdrawnupdated Dec 2025Jan 2025—Dec 2025Dartford8.3
Clay Tye Road Solar Farmsolar farmsolar farm49.9application submitted may be out of dateupdated May 2021Apr 2021—May 2021Thurrock8.4
Clay Tye Farm Energy Storage Facilitybattery storagebattery storage200application submittedupdated Jul 2026May 2026—Jul 2026Havering8.4
Clay Tye Farm Phase 1 - Storage Facilitybattery storagebattery storage49.5operationalupdated Mar 2024Apr 2017granted Mar 2023Mar 2024Havering8.4
Clay Tye Farm Phase 2 - Storage Facilitybattery storagebattery storage49.5operationalupdated Mar 2024Jun 2018granted Feb 2020Mar 2024Havering8.4
Foxhounds Lane, Southfleetbattery storagebattery storage300refusedupdated Jan 2025Apr 2024refused Dec 2024Jan 2025Dartford8.4
Fen Lane, Bulphan Solar Farmsolar farmsolar farm49.9under constructionupdated Mar 2024Jan 2021granted Jul 2021Mar 2024Havering8.4
Cranham Golf Course Solar Parksolar farmsolar farm2.6operationalupdated Feb 2017Jun 2014granted Aug 2015Feb 2017Havering8.8
Cranham Golf Coursesolar farmsolar farm2.6refusedupdated Feb 2015Nov 2014refused Jan 2015Feb 2015Havering8.8
Bulphan Fen Solar Farm & Battery Storagesolar farmsolar farm49.9under constructionupdated Jul 2025Jan 2021granted Oct 2021Jul 2025Thurrock9.1
Clay Tye Farmsolar farmsolar farm15.9refusedupdated May 2016Sep 2014refused Jan 2015May 2016Havering9.2
Broadditch Battery Energybattery storagebattery storage11operationalupdated Feb 2026May 2018granted Aug 2018Feb 2026Dartford9.7
Smaller schemes under 1 MW, mostly rooftop solar (36)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
DSV Road, Stonehouse Lanerooftop solarrooftop solar0.3approved, not builtupdated Nov 2024Sep 2024granted Nov 2024Nov 2024Thurrock1.1
Tesco Store Cygnet Viewrooftop solarrooftop solar0.6approved, not builtupdated Sep 2020Mar 2019granted Apr 2019Sep 2020Thurrock1.3
Ford Retail, Triton Centre Weston Avenuerooftop solarrooftop solar0.8approved, not builtupdated Jan 2023Nov 2022granted Jan 2023Jan 2023Thurrock1.6
Littlebrook DC1, Shield Roadrooftop solarrooftop solar0.6approved, not builtupdated Jul 2025May 2025granted Jul 2025Jul 2025Dartford2.2
Pumping Station, West Thurrock Way - Micro Energy Storagebattery storagebattery storage0.2approved, not builtupdated Nov 2024Sep 2024granted Oct 2024Nov 2024Thurrock2.3
Aveley Landfill, Sandy Lane PV Solar Array & Battery Energy Storagebattery storagebattery storage—approved, not builtupdated Feb 2025Feb 2024granted Jul 2024Feb 2025Thurrock2.3
One Hundred House, Brunel Wayrooftop solarrooftop solar0.8approved, not builtupdated Aug 2023Jul 2023granted Aug 2023Aug 2023Dartford2.8
Riverbridge House, Admirals Parkrooftop solarrooftop solar0.3approved, not builtupdated Jul 2023May 2023granted Jul 2023Jul 2023Dartford3.2
Harris Academy Chafford Hundred, Chafford Hundred Solar Aarrayrooftop solarrooftop solar0.2approved, not builtupdated Apr 2025Feb 2025granted Mar 2025Apr 2025Thurrock3.4
Northern Gateway Distribution Centre, Central Road Northrooftop solarrooftop solar0.8approved, not builtupdated Jan 2024Nov 2023granted Jan 2024Jan 2024Dartford3.7
Pumping Station, Corran Way - Micro Energy Storage Systembattery storagebattery storage0.2approved, not builtupdated Feb 2025Aug 2024granted Jan 2025Feb 2025Thurrock3.7
Northern Gateway Distribution Centre,Central Road Northrooftop solarrooftop solar0.6application submittedJun 2026——Dartford3.7
Littlebrook Hospital, Bow Arrow Lanerooftop solarrooftop solar—approved, not builtupdated Jul 2026Apr 2026granted Jun 2026Jul 2026Dartford4.1
James Watt Wayrooftop solarrooftop solar0.6approved, not builtupdated Nov 2021Nov 2021granted Jan 2022Nov 2021Bexley4.2
Princes Roadrooftop solarrooftop solar0.1approved, not builtupdated Jan 2023Nov 2022granted Jan 2023Jan 2023Dartford4.9
Dartford Grammar School For Boys, West Hillrooftop solarrooftop solar0.2approved, not builtupdated Sep 2024Jul 2024granted Sep 2024Sep 2024Dartford4.9
David Lloyd Sports Centre, Darenth Road Solar Photo Voltaic Systemrooftop solarrooftop solar0.3approved, not builtupdated Jan 2024Nov 2023granted Jan 2024Jan 2024Dartford5.2
Fairfield Pool, Lowfield Streetrooftop solarrooftop solar0.4approved, not builtupdated Oct 2023Jul 2023granted Oct 2023Oct 2023Dartford5.2
Fairfield Centre, Lowfield Streetrooftop solarrooftop solar0.2approved, not builtupdated Oct 2023Aug 2023granted Oct 2023Oct 2023Dartford5.2
Morrisonsrooftop solarrooftop solar0.4approved, not builtupdated Mar 2022Feb 2022granted Apr 2022Mar 2022Thurrock5.3
Tilbury Green Power Stationrooftop solarrooftop solar0.3approved, not builtupdated Mar 2025Dec 2024granted Feb 2025Mar 2025Thurrock6.2
Ceme Campus, Marsh Wayrooftop solarrooftop solar0.9approved, not builtupdated May 2023Feb 2023granted Apr 2023May 2023Havering6.4
Thames Innovation Centre, Veridion Wayrooftop solarrooftop solar0.2approved, not builtupdated Sep 2025May 2025granted Jul 2025Sep 2025Bexley7.2
The Mallrooftop solarrooftop solar—approved, not builtupdated Mar 2026Nov 2025granted Jan 2026Mar 2026Bexley7.5
Bexleyheath Superbowl, Albion Roadrooftop solarrooftop solar0.2approved, not builtupdated Oct 2023Aug 2023granted Oct 2023Oct 2023Bexley7.5
Kimberly Clark Limited, Northfleet Millrooftop solarrooftop solar0.4approved, not builtupdated Nov 2023Aug 2023granted Nov 2023Nov 2023Gravesham7.9
Millbrook Garden Centre, Station Roadrooftop solarrooftop solar0.5approved, not builtupdated Dec 2022Oct 2022granted Dec 2022Dec 2022Dartford8.3
Thames Gateway Park, Choats Roadrooftop solarrooftop solar0.5approved, not builtupdated Jun 2023May 2023granted Jun 2023Jun 2023Barking and Dagenham8.4
JJ Food Service, Orion Park Messina Wayrooftop solarrooftop solar0.6approved, not builtupdated Oct 2023Oct 2023granted Nov 2023Oct 2023Barking and Dagenham8.5
Pooles Lanerooftop solarrooftop solar0.3approved, not builtupdated Nov 2025Jul 2025granted Aug 2025Nov 2025Barking and Dagenham9.0
Bulphan Fen Solar Farm & Battery Storagebattery storagebattery storage—under constructionupdated Jul 2025Jan 2021granted Oct 2021Jul 2025Thurrock9.1
Hunters Hall Primary School, Alibon Roadrooftop solarrooftop solar0.2approved, not builtupdated Jul 2024May 2024granted Jul 2024Jul 2024Barking and Dagenham9.4
Warley Energy Hub, Ockendenbattery storagebattery storage0.2approved, not builtupdated Sep 2025Nov 2024granted Aug 2025Sep 2025Havering9.6
Goresbrook School, Cook Roadrooftop solarrooftop solar0.4approved, not builtupdated Jun 2026Mar 2026granted May 2026Jun 2026Barking and Dagenham9.6
Barking And Dagenham College, Dagenham Roadrooftop solarrooftop solar0.8approved, not builtupdated Jun 2025Mar 2025granted May 2025Jun 2025Barking and Dagenham9.9
Barking & Dagenham College Of Technology, Dagenham Road Solarrooftop solarrooftop solar—no application requiredupdated May 2025Apr 2025—May 2025Barking and Dagenham9.9

Distance from the average position of the RM19 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm101333166
Rooftop solar381342019.9
Wind farm300300
Wind turbine200200
Battery storage233951670

MW in pipeline: pending, approved and under-construction capacity.

How Thurrock decides solar, wind and battery applications

ApplicationsThurrockUK
Decided applications (solar, wind, battery)2810,236
Refused3 (11%)19%
Solar refused2 of 1812%
Onshore wind refused0 of 245%
Battery storage refused1 of 816%
Median time from submission to decision20.3 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Thurrock

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near RM19, 4 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.