Darenth Road (99.9 MW battery storage)

Darenth Road is a 99.9 MW battery storage project in Dartford, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 6 October 2025, not yet built; the record was last updated on 14 October 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

99.9 MWbattery storage
approved, not builtstatus in REPD
14 October 2025record last updated
Dartfordcouncil area

Planning timeline

DateStage
2 May 2025Application submitted
6 October 2025Planning permission granted
6 October 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
99.9 MW
Status (REPD)
approved, not built
Record last updated
14 October 2025
Operator or applicant
Net Zero Marine Services Limited
Planning authority
Dartford
Planning application reference
25/00368/FUL
Address (REPD)
W/O Darenth Road, Dartford
Council area (by location)
Dartford
Time to decision
22 weeks
Name in REPD
Darenth Road - Battery Energy Storage System
REPD reference
18483

Who decides

ApplicationsDartfordUK
Decided applications (solar, wind, battery)1810,236
Refused1 (6%)19%
Solar refused0 of 1312%
Battery storage refused1 of 516%
Median time from submission to decision9.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bean Lanebattery storage104application withdrawn2.1
Land Adjacent Davanden Kennelsbattery storage7.5abandoned2.6
Albion Roadbattery storage5application withdrawn3.2
Littlebrook Battery Storagebattery storage7.5operational3.2
Horton Wood Solar parksolar farm49.9approved, not built4.6
Manor Farm, Dartford Roadbattery storage212application submitted5.4
New Barn Roadbattery storage35approved, not built5.6
Dartford BESSbattery storage300application withdrawn5.7
Foxhounds Lane, Southfleetbattery storage300refused6.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.4326, 0.2322).