Land Adjacent Davanden Kennels (7.5 MW battery storage)

Land Adjacent Davanden Kennels is a 7.5 MW battery storage project in Dartford, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 12 February 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7.5 MWbattery storage
abandonedstatus in REPD
12 February 2020record last updated
Dartfordcouncil area

Planning timeline

DateStage
3 May 2018Application submitted
28 June 2021Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
7.5 MW
Status (REPD)
abandoned
Record last updated
12 February 2020
Operator or applicant
Arlington Energy (formerly Enso Energy)
Planning authority
Dartford
Planning application reference
18/00418/FUL
Address (REPD)
Land adj Davanden Kennels, Cotton Lane, Greenhithe, Kent
Council area (by location)
Dartford
REPD reference
7031

Who decides

ApplicationsDartfordUK
Decided applications (solar, wind, battery)1810,236
Refused1 (6%)19%
Solar refused0 of 1312%
Battery storage refused1 of 516%
Median time from submission to decision9.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Albion Roadbattery storage5application withdrawn1.0
Littlebrook Battery Storagebattery storage7.5operational1.0
Bean Lanebattery storage104application withdrawn1.3
Darenth Roadbattery storage99.9approved, not built2.6
New Barn Roadbattery storage35approved, not built5.2
Dartford BESSbattery storage300application withdrawn5.2
Foxhounds Lane, Southfleetbattery storage300refused5.4
Thames Way, Northfleetbattery storage100application submitted5.7
Tilbury Dockswind farm12operational5.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.4509, 0.2547).