Littlebrook Battery Storage (7.5 MW)

Littlebrook Battery Storage is a 7.5 MW battery storage project in Dartford, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 December 2017; the record was last updated on 2 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7.5 MWbattery storage
operationalstatus in REPD
2 February 2026record last updated
Dartfordcouncil area

Planning timeline

DateStage
14 July 2016Application submitted
12 September 2016Planning permission granted
1 January 2017Construction started
1 December 2017Operational

Project details

Technology
battery storage (stand-alone storage)
Capacity
7.5 MW
Status (REPD)
operational
Record last updated
2 February 2026
Operator or applicant
Camborne Energy / Noriker Power
Planning authority
Dartford
Planning application reference
16/01136/FUL
Address (REPD)
Land Off Albion Road Dartford
Council area (by location)
Dartford
Time to decision
9 weeks
REPD reference
20327

Who decides

ApplicationsDartfordUK
Decided applications (solar, wind, battery)1810,236
Refused1 (6%)19%
Solar refused0 of 1312%
Battery storage refused1 of 516%
Median time from submission to decision9.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Albion Roadbattery storage5application withdrawn<0.1
Land Adjacent Davanden Kennelsbattery storage7.5abandoned1.0
Bean Lanebattery storage104application withdrawn2.3
Darenth Roadbattery storage99.9approved, not built3.2
Aveley Landfill, Sandy Lane PV Solar Array & Battery Energy Storagesolar farm16approved, not built5.0
New Barn Roadbattery storage35approved, not built6.1
Dartford BESSbattery storage300application withdrawn6.1
Tilbury Dockswind farm12operational6.1
Foxhounds Lane, Southfleetbattery storage300refused6.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.4593, 0.2489).