New Barn Road (35 MW battery storage)

New Barn Road is a 35 MW battery storage project in Dartford, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 15 February 2024, not yet built; the record was last updated on 19 February 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

35 MWbattery storage
approved, not builtstatus in REPD
19 February 2024record last updated
Dartfordcouncil area

Planning timeline

DateStage
7 August 2023Application submitted
15 February 2024Planning permission granted
15 February 2027Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
35 MW
Status (REPD)
approved, not built
Record last updated
19 February 2024
Operator or applicant
Aton Energy Development (Northfleet) Limited
Planning authority
Dartford
Planning application reference
23/00863/FUL
Address (REPD)
East Side Of New Barn Road, Gravesend
Council area (by location)
Dartford
Time to decision
27 weeks
Name in REPD
New Barn Road - Battery Energy Storage Facility
REPD reference
14650

Who decides

ApplicationsDartfordUK
Decided applications (solar, wind, battery)1810,236
Refused1 (6%)19%
Solar refused0 of 1312%
Battery storage refused1 of 516%
Median time from submission to decision9.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Dartford BESSbattery storage300application withdrawn<0.1
Foxhounds Lane, Southfleetbattery storage300refused0.6
Broadditch Battery Energybattery storage11operational1.5
Thames Way, Northfleetbattery storage100application submitted2.3
Bean Lanebattery storage104application withdrawn4.1
Tilbury Dockswind farm12operational4.4
Land Adjacent Davanden Kennelsbattery storage7.5abandoned5.2
Darenth Roadbattery storage99.9approved, not built5.6
Idleigh Court Road, New Ash Greensolar farm49.9application submitted5.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.4208, 0.3115).