Broadditch Battery Energy (11 MW)

Broadditch Battery Energy is an 11 MW battery storage project in Dartford, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 March 2023; the record was last updated on 2 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11 MWbattery storage
operationalstatus in REPD
2 February 2026record last updated
Dartfordcouncil area

Planning timeline

DateStage
14 May 2018Application submitted
16 August 2018Planning permission granted
1 March 2023Operational

Project details

Technology
battery storage (stand-alone storage)
Capacity
11 MW
Status (REPD)
operational
Record last updated
2 February 2026
Operator or applicant
Harmony Energy
Planning authority
Dartford
Planning application reference
18/00637/FUL
Address (REPD)
Land At Broadditch Farm New Barn Road Southfleet
Council area (by location)
Dartford
Time to decision
13 weeks
REPD reference
20328

Who decides

ApplicationsDartfordUK
Decided applications (solar, wind, battery)1810,236
Refused1 (6%)19%
Solar refused0 of 1312%
Battery storage refused1 of 516%
Median time from submission to decision9.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Foxhounds Lane, Southfleetbattery storage300refused1.3
Dartford BESSbattery storage300application withdrawn1.4
New Barn Roadbattery storage35approved, not built1.5
Thames Way, Northfleetbattery storage100application submitted2.6
Tilbury Dockswind farm12operational4.9
Idleigh Court Road, New Ash Greensolar farm49.9application submitted5.0
Bean Lanebattery storage104application withdrawn5.6
Thurrock Flexible Generation Plantbattery storage150operational6.2
Land Adjacent Davanden Kennelsbattery storage7.5abandoned6.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.4134, 0.3288).