Tilbury Docks (12 MW wind farm)
Tilbury Docks is a 12 MW wind farm project in Thurrock, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 25 March 2013; the record was last updated on 4 July 2017.
12 MWwind farm
operationalstatus in REPD
4 July 2017record last updated
Thurrockcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 20 December 2007 | Application submitted |
| 13 May 2008 | Planning permission granted |
| 28 September 2012 | Construction started |
| 25 March 2013 | Operational |
Project details
- Technology
- wind farm
- Capacity
- 12 MW
- Status (REPD)
- operational
- Record last updated
- 4 July 2017
- Operator or applicant
- Scottish Equity Partners
- Planning authority
- Thurrock
- Planning application reference
- 07/01328/TTGFUL
- Turbines
- 4
- Address (REPD)
- Installed from the Dock entrance along to the GradeII listed Cruise Terminal, Tilbury Docks, Tilbury
- Council area (by location)
- Thurrock
- Time to decision
- 21 weeks
- REPD reference
- 3982
Who decides
| Applications | Thurrock | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 28 | 10,236 |
| Refused | 3 (11%) | 19% |
| Solar refused | 2 of 18 | 12% |
| Onshore wind refused | 0 of 2 | 45% |
| Battery storage refused | 1 of 8 | 16% |
| Median time from submission to decision | 20.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 0 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Thames Way, Northfleet | battery storage | 100 | application submitted | 2.3 |
| The Place Solar Farm | solar farm | 23.2 | refused | 2.8 |
| Thurrock Flexible Generation Plant | battery storage | 150 | operational | 3.3 |
| Foxhounds Lane, Southfleet | battery storage | 300 | refused | 3.9 |
| New Barn Road | battery storage | 35 | approved, not built | 4.4 |
| Dartford BESS | battery storage | 300 | application withdrawn | 4.4 |
| Broadditch Battery Energy | battery storage | 11 | operational | 4.9 |
| Bean Lane | battery storage | 104 | application withdrawn | 5.6 |
| Land Adjacent Davanden Kennels | battery storage | 7.5 | abandoned | 5.7 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.4573, 0.3368).