Tilbury Docks (12 MW wind farm)

Tilbury Docks is a 12 MW wind farm project in Thurrock, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 25 March 2013; the record was last updated on 4 July 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12 MWwind farm
operationalstatus in REPD
4 July 2017record last updated
Thurrockcouncil area

Planning timeline

DateStage
20 December 2007Application submitted
13 May 2008Planning permission granted
28 September 2012Construction started
25 March 2013Operational

Project details

Technology
wind farm
Capacity
12 MW
Status (REPD)
operational
Record last updated
4 July 2017
Operator or applicant
Scottish Equity Partners
Planning authority
Thurrock
Planning application reference
07/01328/TTGFUL
Turbines
4
Address (REPD)
Installed from the Dock entrance along to the GradeII listed Cruise Terminal, Tilbury Docks, Tilbury
Council area (by location)
Thurrock
Time to decision
21 weeks
REPD reference
3982

Who decides

ApplicationsThurrockUK
Decided applications (solar, wind, battery)2810,236
Refused3 (11%)19%
Solar refused2 of 1812%
Onshore wind refused0 of 245%
Battery storage refused1 of 816%
Median time from submission to decision20.3 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Thames Way, Northfleetbattery storage100application submitted2.3
The Place Solar Farmsolar farm23.2refused2.8
Thurrock Flexible Generation Plantbattery storage150operational3.3
Foxhounds Lane, Southfleetbattery storage300refused3.9
New Barn Roadbattery storage35approved, not built4.4
Dartford BESSbattery storage300application withdrawn4.4
Broadditch Battery Energybattery storage11operational4.9
Bean Lanebattery storage104application withdrawn5.6
Land Adjacent Davanden Kennelsbattery storage7.5abandoned5.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.4573, 0.3368).