Aveley Landfill, Sandy Lane PV Solar Array & Battery Energy Storage (16 MW)

Aveley Landfill, Sandy Lane PV Solar Array & Battery Energy Storage is a 16 MW solar farm project in Thurrock, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 24 July 2024, not yet built; the record was last updated on 11 February 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

16 MWsolar farm
approved, not builtstatus in REPD
11 February 2025record last updated
Thurrockcouncil area

Planning timeline

DateStage
5 February 2024Application submitted
24 July 2024Planning permission granted

Project details

Technology
solar farm
Capacity
16 MW
Status (REPD)
approved, not built
Record last updated
11 February 2025
Operator or applicant
Infinis Energy Services Limited
Planning authority
Thurrock
Planning application reference
24/00141/FUL
Site area
22.7 ha
Address (REPD)
Infinis Ltd Aveley Landfill Sandy Lane Aveley
Council area (by location)
Thurrock
Time to decision
24 weeks
Name in REPD
Aveley Landfill, Sandy Lane - PV Solar Array & Battery Energy Storage
REPD reference
15828

Who decides

ApplicationsThurrockUK
Decided applications (solar, wind, battery)2810,236
Refused3 (11%)19%
Solar refused2 of 1812%
Onshore wind refused0 of 245%
Battery storage refused1 of 816%
Median time from submission to decision20.3 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Medebridge Road Solar Farmsolar farm49.9operational3.9
Littlebrook Battery Storagebattery storage7.5operational5.0
Albion Roadbattery storage5application withdrawn5.0
Riverside Energy Parkbattery storage20approved, not built5.8
Land Adjacent Davanden Kennelsbattery storage7.5abandoned5.9
Ockendon Landfill Solar Farmsolar farm38operational6.2
Ford Wind Park - Dagenhamwind farm5.9operational6.2
Clay Tye Farm Phase 1 - Storage Facilitybattery storage49.5operational6.7
Clay Tye Farm Phase 2 - Storage Facilitybattery storage49.5operational6.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.5033, 0.2373).