Energy Projects Near You

Clay Tye Farm Phase 1 - Storage Facility (49.5 MW)

Clay Tye Farm Phase 1 - Storage Facility is a 49.5 MW battery storage project in Havering, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 22 March 2024; the record was last updated on 27 March 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.5 MWbattery storage
operationalstatus in REPD
27 March 2024record last updated
Haveringcouncil area

Planning timeline

DateStage
28 April 2017Application submitted
18 July 2017Refused by the planning authority
1 July 2022Construction started
6 March 2023Planning permission granted
22 March 2024Operational

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.5 MW
Status (REPD)
operational
Record last updated
27 March 2024
Operator or applicant
Harmony Energy Storage
Planning authority
Havering
Planning application reference
P0611.17
Address (REPD)
Clay Tye Farm, Clay Tye Road, Upminster
Council area (by location)
Havering
Time to decision
305 weeks
REPD reference
11720

Who decides

ApplicationsHaveringUK
Decided applications (solar, wind, battery)1310,236
Refused5 (38%)19%
Solar refused3 of 1012%
Battery storage refused2 of 316%
Median time from submission to decision17.1 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Clay Tye Farm Energy Storage Facilitybattery storage200application submitted<0.1
Clay Tye Farm Phase 2 - Storage Facilitybattery storage49.5operational<0.1
Clay Tye Farmsolar farm15.9refused0.9
Fen Lane, Bulphan Solar Farmsolar farm49.9under construction2.2
Clay Tye Road Solar Farmsolar farm49.9application submitted2.3
Ockendon Landfill Solar Farmsolar farm38operational3.3
Bulphan Fen Solar Farm & Battery Storagesolar farm49.9under construction3.4
Medebridge Road Solar Farmsolar farm49.9operational4.6
Aveley Landfill, Sandy Lane PV Solar Array & Battery Energy Storagesolar farm16approved, not built6.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.5518, 0.2943).