Energy Projects Near You

Renewable energy projects in Havering

14 solar, wind or battery projects of 150 kW or more are located in Havering (REPD, July 2026 extract): 1 pending, 7 approved but not running, 4 operational and 2 refused. The council refused 5 of 13 decided applications (38%; UK 19%), with a median 17 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

14projects in the council area
1awaiting a decision
7approved, not running
38%of decisions refused

How Havering decides

ApplicationsHaveringUK
Decided applications (solar, wind, battery)1310,236
Refused5 (38%)19%
Solar refused3 of 1012%
Battery storage refused2 of 316%
Median time from submission to decision17.1 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

Projects in Havering

Projects of 1 MW and more (7)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Clay Tye Farm Energy Storage Facilitybattery storagebattery storage200application submittedupdated Jul 2026May 2026—Jul 2026
Fen Lane, Bulphan Solar Farmsolar farmsolar farm49.9under constructionupdated Mar 2024Jan 2021granted Jul 2021Mar 2024
Clay Tye Farm Phase 1 - Storage Facilitybattery storagebattery storage49.5operationalupdated Mar 2024Apr 2017granted Mar 2023Mar 2024
Clay Tye Farm Phase 2 - Storage Facilitybattery storagebattery storage49.5operationalupdated Mar 2024Jun 2018granted Feb 2020Mar 2024
Clay Tye Farmsolar farmsolar farm15.9refusedupdated May 2016Sep 2014refused Jan 2015May 2016
Cranham Golf Course Solar Parksolar farmsolar farm2.6operationalupdated Feb 2017Jun 2014granted Aug 2015Feb 2017
Cranham Golf Coursesolar farmsolar farm2.6refusedupdated Feb 2015Nov 2014refused Jan 2015Feb 2015
Smaller schemes under 1 MW, mostly rooftop solar (7)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Ceme Campus, Marsh Wayrooftop solarrooftop solar0.9approved, not builtupdated May 2023Feb 2023granted Apr 2023May 2023
Liberty Shopping Centre, Western Roadrooftop solarrooftop solar0.5approved, not builtupdated Apr 2024Jan 2024granted Mar 2024Apr 2024
David Lloyd Leisure, Gidea Parkrooftop solarrooftop solar0.4approved, not builtupdated Aug 2023Jun 2023granted Jul 2023Aug 2023
Central Park Leisurerooftop solarrooftop solar0.4approved, not builtupdated Jan 2025Oct 2024granted Nov 2024Jan 2025
Bower Park Academyrooftop solarrooftop solar0.3operationalupdated Dec 2021Jan 2021granted Oct 2021Dec 2021
Romford Halal Meats, Folkes Lanerooftop solarrooftop solar0.2approved, not built may be out of dateupdated Jan 2023Sep 2022granted Dec 2022Jan 2023
Warley Energy Hub, Ockendenbattery storagebattery storage0.2approved, not builtupdated Sep 2025Nov 2024granted Aug 2025Sep 2025

Postcode districts in Havering

DistrictProjects within 10 kmPendingApprovedOperational
RM14743010
RM2414268
RM3294157
RM5392314
RM75653711
RM114953011
RM126154013
RM138195114
RM145333413

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Havering by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.