Energy Projects Near You

Clay Tye Road Solar Farm (49.9 MW)

Clay Tye Road Solar Farm is a 49.9 MW solar farm project in Thurrock, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 27 April 2021, no decision recorded; the record was last updated on 18 May 2021. The application was submitted more than two years ago and is still shown as pending; it may have been decided since. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
application submittedmay be out of datestatus in REPD
18 May 2021record last updated
Thurrockcouncil area

The application was submitted more than two years ago and is still shown as pending; it may have been decided since. 32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided.

Planning timeline

DateStage
27 April 2021Application submitted

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
application submitted
Record last updated
18 May 2021
Operator or applicant
REG Windpower Limited
Planning authority
Havering
Planning application reference
P0814.21
Site area
8.0 ha
Address (REPD)
E/O Claytye Road, Warley Sub-Station, Clay Tye Road, Upminster
Council area (by location)
Thurrock
Name in REPD
Clay Tye Road - Solar Farm
REPD reference
9035

Who decides

ApplicationsHaveringUK
Decided applications (solar, wind, battery)1310,236
Refused5 (38%)19%
Solar refused3 of 1012%
Battery storage refused2 of 316%
Median time from submission to decision17.1 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Fen Lane, Bulphan Solar Farmsolar farm49.9under construction<0.1
Bulphan Fen Solar Farm & Battery Storagesolar farm49.9under construction1.2
Ockendon Landfill Solar Farmsolar farm38operational1.6
Clay Tye Farmsolar farm15.9refused2.2
Clay Tye Farm Phase 1 - Storage Facilitybattery storage49.5operational2.3
Clay Tye Farm Energy Storage Facilitybattery storage200application submitted2.3
Clay Tye Farm Phase 2 - Storage Facilitybattery storage49.5operational2.3
Medebridge Road Solar Farmsolar farm49.9operational4.0
Lime Kilns Energy Centrebattery storage6approved, not built5.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.5408, 0.3222).