Energy Projects Near You

Medebridge Road Solar Farm (49.9 MW)

Medebridge Road Solar Farm is a 49.9 MW solar farm project in Thurrock, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 September 2025; the record was last updated on 11 November 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
operationalstatus in REPD
11 November 2025record last updated
Thurrockcouncil area

Planning timeline

DateStage
14 February 2022Application submitted
10 May 2022Planning permission granted
1 April 2024Construction started
1 September 2025Operational

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
operational
Record last updated
11 November 2025
Operator or applicant
Medebridge Solar
Planning authority
Thurrock
Planning application reference
21/02159/FUL
Site area
90.0 ha
Address (REPD)
Fen Lane And Medebridge Road
Council area (by location)
Thurrock
Time to decision
12 weeks
Name in REPD
Medebridge Road - Solar Farm
REPD reference
10369

Who decides

ApplicationsThurrockUK
Decided applications (solar, wind, battery)2810,236
Refused3 (11%)19%
Solar refused2 of 1812%
Onshore wind refused0 of 245%
Battery storage refused1 of 816%
Median time from submission to decision20.3 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Ockendon Landfill Solar Farmsolar farm38operational2.6
Aveley Landfill, Sandy Lane PV Solar Array & Battery Energy Storagesolar farm16approved, not built3.9
Clay Tye Road Solar Farmsolar farm49.9application submitted4.0
Fen Lane, Bulphan Solar Farmsolar farm49.9under construction4.0
Clay Tye Farm Phase 1 - Storage Facilitybattery storage49.5operational4.6
Clay Tye Farm Phase 2 - Storage Facilitybattery storage49.5operational4.6
Clay Tye Farm Energy Storage Facilitybattery storage200application submitted4.6
Bulphan Fen Solar Farm & Battery Storagesolar farm49.9under construction4.6
Clay Tye Farmsolar farm15.9refused5.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.5106, 0.2919).