Lime Kilns Energy Centre (6 MW battery storage)

Lime Kilns Energy Centre is a 6 MW battery storage project in Thurrock, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 19 December 2024, not yet built; the record was last updated on 8 July 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6 MWbattery storage
approved, not builtstatus in REPD
8 July 2025record last updated
Thurrockcouncil area

Planning timeline

DateStage
8 October 2024Application submitted
19 December 2024Planning permission granted
19 December 2027Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
6 MW
Status (REPD)
approved, not built
Record last updated
8 July 2025
Operator or applicant
Flexitricity
Planning authority
Thurrock
Planning application reference
24/01069/FUL
Address (REPD)
Flexitricity Lime Kilns Energy Centre Lower Dunton Road Bulphan
Council area (by location)
Thurrock
Time to decision
10 weeks
Name in REPD
Lime Kilns Energy Centre - Battery Energy Storage
REPD reference
17397

Who decides

ApplicationsThurrockUK
Decided applications (solar, wind, battery)2810,236
Refused3 (11%)19%
Solar refused2 of 1812%
Onshore wind refused0 of 245%
Battery storage refused1 of 816%
Median time from submission to decision20.3 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Fairwind Farmsolar farm10operational0.8
Lower Dunton Road Battery Storage Facilitybattery storage28operational1.0
Lower Dunton Roadbattery storage368application submitted1.1
Ford Research And Engineering Centre, Dunton Solar Farmsolar farm5.2operational2.8
Crouch Solar Farmsolar farm49.9operational3.8
Bulphan Fen Solar Farm & Battery Storagesolar farm49.9under construction4.2
Fen Lane, Bulphan Solar Farmsolar farm49.9under construction5.2
Clay Tye Road Solar Farmsolar farm49.9application submitted5.3
Whites Farmbattery storage49.9refused5.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.5572, 0.3935).