Solar, wind and battery projects near Brentwood (CM13)
40 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of CM13 (Brentwood): 4 are waiting for a planning decision, 19 approved but not yet running, 12 operational. The largest live scheme is Lower Dunton Road (368 MW battery storage, application submitted on 25 October 2024, no decision recorded), 6.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of CM13
Projects of 1 MW and more (27)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Solar Farm at Billericay Solar Farm North Of Rayleigh Road Huttonsolar farm | solar farm | 15 | approved, not builtupdated Nov 2025 | Nov 2024 | granted Apr 2025 | Nov 2025 | Brentwood | 1.9 |
| Hutton Battery Storage (Lower Road)battery storage | battery storage | 10 | operationalupdated Mar 2026 | Sep 2017 | granted Dec 2017 | Mar 2026 | Brentwood | 2.9 |
| Brentwood nergy Storage Systembattery storage | battery storage | 49.9 | approved, not built may be out of dateupdated Jul 2022 | Dec 2020 | granted May 2021 | Jul 2022 | Brentwood | 3.2 |
| Land at Havering Grove Farmsolar farm | solar farm | 5 | refused on appealupdated May 2016 | Feb 2015 | refused Jun 2015 | May 2016 | Brentwood | 3.3 |
| Crouch Solar Farmsolar farm | solar farm | 49.9 | operationalupdated Oct 2024 | May 2021 | granted Dec 2021 | Oct 2024 | Brentwood | 3.8 |
| Crouch Solar Farmbattery storage | battery storage | 49.9 | operationalupdated Oct 2024 | May 2021 | granted Dec 2021 | Oct 2024 | Brentwood | 3.8 |
| Great Cowbridge Grange Farm, London Road Solar Farmsolar farm | solar farm | 10 | approved, not builtupdated May 2025 | Sep 2024 | granted May 2025 | May 2025 | Basildon | 4.0 |
| Ford Research And Engineering Centre, Dunton Solar Farmsolar farm | solar farm | 5.2 | operationalupdated Mar 2025 | Jun 2022 | granted Feb 2023 | Mar 2025 | Basildon | 5.9 |
| Lower Dunton Road Battery Storage Facilitybattery storage | battery storage | 28 | operationalupdated Feb 2026 | Oct 2020 | granted Feb 2021 | Feb 2026 | Basildon | 6.5 |
| Lower Dunton Roadbattery storage | battery storage | 368 | application submittedupdated Nov 2024 | Oct 2024 | — | Nov 2024 | Basildon | 6.5 |
| Fairwind Farmsolar farm | solar farm | 10 | operationalupdated Jul 2015 | Jun 2013 | granted Nov 2013 | Jul 2015 | Basildon | 6.7 |
| Clay Tye Farmsolar farm | solar farm | 15.9 | refusedupdated May 2016 | Sep 2014 | refused Jan 2015 | May 2016 | Havering | 6.9 |
| Cranham Golf Course Solar Parksolar farm | solar farm | 2.6 | operationalupdated Feb 2017 | Jun 2014 | granted Aug 2015 | Feb 2017 | Havering | 7.3 |
| Cranham Golf Coursesolar farm | solar farm | 2.6 | refusedupdated Feb 2015 | Nov 2014 | refused Jan 2015 | Feb 2015 | Havering | 7.3 |
| Lime Kilns Energy Centrebattery storage | battery storage | 6 | approved, not builtupdated Jul 2025 | Oct 2024 | granted Dec 2024 | Jul 2025 | Thurrock | 7.5 |
| Outwood Farm (Phase 2)solar farm | solar farm | 7 | approved, not builtupdated Jan 2020 | Aug 2014 | granted Dec 2014 | Jan 2020 | Basildon | 7.5 |
| Outwood Farm (Phase 1)solar farm | solar farm | 5 | operationalupdated Jul 2016 | Aug 2014 | granted Dec 2014 | Jul 2016 | Basildon | 7.5 |
| Barleylands Solar Farmsolar farm | solar farm | 17 | approved, not builtupdated Oct 2024 | Nov 2023 | granted Oct 2024 | Oct 2024 | Basildon | 7.6 |
| Clay Tye Farm Energy Storage Facilitybattery storage | battery storage | 200 | application submittedupdated Jul 2026 | May 2026 | — | Jul 2026 | Havering | 7.7 |
| Clay Tye Farm Phase 1 - Storage Facilitybattery storage | battery storage | 49.5 | operationalupdated Mar 2024 | Apr 2017 | granted Mar 2023 | Mar 2024 | Havering | 7.7 |
| Clay Tye Farm Phase 2 - Storage Facilitybattery storage | battery storage | 49.5 | operationalupdated Mar 2024 | Jun 2018 | granted Feb 2020 | Mar 2024 | Havering | 7.7 |
| Whites Farmbattery storage | battery storage | 49.9 | refusedupdated Aug 2023 | Jul 2022 | refused Jul 2023 | Aug 2023 | Basildon | 7.9 |
| Fen Lane, Bulphan Solar Farmsolar farm | solar farm | 49.9 | under constructionupdated Mar 2024 | Jan 2021 | granted Jul 2021 | Mar 2024 | Havering | 8.3 |
| Clay Tye Road Solar Farmsolar farm | solar farm | 49.9 | application submitted may be out of dateupdated May 2021 | Apr 2021 | — | May 2021 | Thurrock | 8.3 |
| Bulphan Fen Solar Farm & Battery Storagesolar farm | solar farm | 49.9 | under constructionupdated Jul 2025 | Jan 2021 | granted Oct 2021 | Jul 2025 | Thurrock | 8.4 |
| Crays Hall Farm Solar Arrayssolar farm | solar farm | 25.6 | operationalupdated Jun 2026 | Mar 2022 | granted Aug 2023 | Jun 2026 | Basildon | 8.9 |
| Ockendon Landfill Solar Farmsolar farm | solar farm | 38 | operationalupdated Sep 2023 | Jul 2014 | granted Jan 2016 | Sep 2023 | Thurrock | 10.0 |
Smaller schemes under 1 MW, mostly rooftop solar (13)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| The Marillac, Eagle Wayrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jul 2025 | Apr 2025 | granted Jun 2025 | Jul 2025 | Brentwood | 2.9 |
| Peri Limited, Greenways Solar Photovoltaicsrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Jan 2023 | Nov 2022 | granted Dec 2022 | Jan 2023 | Brentwood | 4.6 |
| Romford Halal Meats, Folkes Lanerooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Jan 2023 | Sep 2022 | granted Dec 2022 | Jan 2023 | Havering | 6.2 |
| Warley Energy Hub, Ockendenbattery storage | battery storage | 0.2 | approved, not builtupdated Sep 2025 | Nov 2024 | granted Aug 2025 | Sep 2025 | Havering | 6.5 |
| Barleylands Solar Farmbattery storage | battery storage | — | approved, not builtupdated Oct 2024 | Nov 2023 | granted Oct 2024 | Oct 2024 | Basildon | 7.6 |
| Central Park Leisurerooftop solar | rooftop solar | 0.4 | approved, not builtupdated Jan 2025 | Oct 2024 | granted Nov 2024 | Jan 2025 | Havering | 7.8 |
| Miles Gray Road, Steeple View - Micro Energy Storagebattery storage | battery storage | 0.2 | approved, not builtupdated May 2026 | Jan 2026 | granted Mar 2026 | May 2026 | Basildon | 8.4 |
| Bulphan Fen Solar Farm & Battery Storagebattery storage | battery storage | — | under constructionupdated Jul 2025 | Jan 2021 | granted Oct 2021 | Jul 2025 | Thurrock | 8.4 |
| David Lloyd Leisure, Gidea Parkrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Aug 2023 | Jun 2023 | granted Jul 2023 | Aug 2023 | Havering | 9.0 |
| David Lloyd Leisure, Festival Way - Soalr Panelsrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Feb 2024 | Dec 2023 | granted Feb 2024 | Feb 2024 | Basildon | 9.1 |
| Ambrose Close & Gloucester Park, Broadmaynebattery storage | battery storage | 0.2 | application withdrawnupdated Dec 2025 | Feb 2025 | — | Dec 2025 | Basildon | 9.4 |
| Endeavour Point, Endeavour Driverooftop solar | rooftop solar | 0.5 | application submittedupdated Jan 2025 | Nov 2024 | — | Jan 2025 | Basildon | 9.5 |
| Langford Bridge Farm, Ongar Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Feb 2025 | Dec 2024 | granted Feb 2025 | Feb 2025 | Brentwood | 9.8 |
Distance from the average position of the CM13 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 17 | 1 | 6 | 7 | 3 | 199 |
| Rooftop solar | 8 | 1 | 7 | 0 | 0 | 2.6 |
| Battery storage | 15 | 2 | 6 | 5 | 1 | 624 |
MW in pipeline: pending, approved and under-construction capacity.
How Brentwood decides solar, wind and battery applications
Brentwood has 9 decided solar, wind or battery applications in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near CM13, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.