Energy Projects Near You

Great Cowbridge Grange Farm, London Road Solar Farm (10 MW)

Great Cowbridge Grange Farm, London Road Solar Farm is a 10 MW solar farm project in Basildon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 1 May 2025, not yet built; the record was last updated on 12 May 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWsolar farm
approved, not builtstatus in REPD
12 May 2025record last updated
Basildoncouncil area

Planning timeline

DateStage
27 September 2024Application submitted
1 May 2025Planning permission granted
1 May 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
10 MW
Status (REPD)
approved, not built
Record last updated
12 May 2025
Operator or applicant
Conrad Energy (Developments) Limited
Planning authority
Basildon
Planning application reference
24/01262/FULL
Site area
16.6 ha
Address (REPD)
Great Cowbridge Grange Farm London Road
Council area (by location)
Basildon
Time to decision
31 weeks
Name in REPD
Great Cowbridge Grange Farm, London Road - Solar Farm
REPD reference
17349

Who decides

ApplicationsBasildonUK
Decided applications (solar, wind, battery)2010,236
Refused2 (10%)19%
Solar refused1 of 1212%
Battery storage refused1 of 816%
Median time from submission to decision16.8 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land at Havering Grove Farmsolar farm5refused on appeal0.8
Brentwood nergy Storage Systembattery storage49.9approved, not built2.6
Hutton Battery Storage (Lower Road)battery storage10operational2.7
Outwood Farm (Phase 2)solar farm7approved, not built3.8
Outwood Farm (Phase 1)solar farm5operational3.8
Solar Farm at Billericay Solar Farm North Of Rayleigh Road Huttonsolar farm15approved, not built4.2
Crouch Solar Farmsolar farm49.9operational4.3
Barleylands Solar Farmsolar farm17approved, not built4.7
Ford Research And Engineering Centre, Dunton Solar Farmsolar farm5.2operational5.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6274, 0.3919).