Solar, wind and battery projects near Ingatestone (CM4)
20 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of CM4 (Brentwood): 1 is waiting for a planning decision, 11 approved but not yet running, 5 operational. The largest live scheme is Brentwood nergy Storage System (49.9 MW battery storage, approved on 21 May 2021, not yet built; REPD status may be out of date), 4.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of CM4
Projects of 1 MW and more (14)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Brentwood nergy Storage Systembattery storage | battery storage | 49.9 | approved, not built may be out of dateupdated Jul 2022 | Dec 2020 | granted May 2021 | Jul 2022 | Brentwood | 4.3 |
| Hutton Battery Storage (Lower Road)battery storage | battery storage | 10 | operationalupdated Mar 2026 | Sep 2017 | granted Dec 2017 | Mar 2026 | Brentwood | 4.7 |
| Land at Havering Grove Farmsolar farm | solar farm | 5 | refused on appealupdated May 2016 | Feb 2015 | refused Jun 2015 | May 2016 | Brentwood | 5.3 |
| Great Cowbridge Grange Farm, London Road Solar Farmsolar farm | solar farm | 10 | approved, not builtupdated May 2025 | Sep 2024 | granted May 2025 | May 2025 | Basildon | 5.3 |
| Solar Farm at Billericay Solar Farm North Of Rayleigh Road Huttonsolar farm | solar farm | 15 | approved, not builtupdated Nov 2025 | Nov 2024 | granted Apr 2025 | Nov 2025 | Brentwood | 6.2 |
| Outwood Farm (Phase 2)solar farm | solar farm | 7 | approved, not builtupdated Jan 2020 | Aug 2014 | granted Dec 2014 | Jan 2020 | Basildon | 7.1 |
| Outwood Farm (Phase 1)solar farm | solar farm | 5 | operationalupdated Jul 2016 | Aug 2014 | granted Dec 2014 | Jul 2016 | Basildon | 7.1 |
| Crays Hall Farm Solar Arrayssolar farm | solar farm | 25.6 | operationalupdated Jun 2026 | Mar 2022 | granted Aug 2023 | Jun 2026 | Basildon | 9.0 |
| Barleylands Solar Farmsolar farm | solar farm | 17 | approved, not builtupdated Oct 2024 | Nov 2023 | granted Oct 2024 | Oct 2024 | Basildon | 9.1 |
| Ongar Landfill Ground mounted solar photovoltaicsolar farm | solar farm | 8.8 | application withdrawnupdated May 2022 | Feb 2021 | — | May 2022 | Brentwood | 9.3 |
| Crouch Solar Farmsolar farm | solar farm | 49.9 | operationalupdated Oct 2024 | May 2021 | granted Dec 2021 | Oct 2024 | Brentwood | 9.5 |
| Crouch Solar Farmbattery storage | battery storage | 49.9 | operationalupdated Oct 2024 | May 2021 | granted Dec 2021 | Oct 2024 | Brentwood | 9.5 |
| Canon Barns Road Solar Parksolar farm | solar farm | 8 | approved, not built may be out of dateupdated Feb 2022 | Mar 2021 | granted Jan 2022 | Feb 2022 | Chelmsford | 9.7 |
| Whites Farmbattery storage | battery storage | 49.9 | refusedupdated Aug 2023 | Jul 2022 | refused Jul 2023 | Aug 2023 | Basildon | 9.8 |
Smaller schemes under 1 MW, mostly rooftop solar (6)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Robjohns Road - Micro Energy Storagebattery storage | battery storage | 0.2 | approved, not builtupdated Apr 2026 | Dec 2025 | granted Mar 2026 | Apr 2026 | Chelmsford | 6.6 |
| Robjohns Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Dec 2021 | Sep 2021 | granted Oct 2021 | Dec 2021 | Chelmsford | 6.8 |
| Sewage Treatment Works, Lawford Lane - Micro Energy Storagebattery storage | battery storage | 0.2 | application submittedupdated Sep 2024 | Aug 2024 | — | Sep 2024 | Chelmsford | 6.9 |
| Verge Fronting, Westway - Micro Energy Storagebattery storage | battery storage | 0.2 | approved, not builtupdated Apr 2026 | Nov 2025 | granted Feb 2026 | Apr 2026 | Chelmsford | 7.0 |
| Barleylands Solar Farmbattery storage | battery storage | — | approved, not builtupdated Oct 2024 | Nov 2023 | granted Oct 2024 | Oct 2024 | Basildon | 9.1 |
| Langford Bridge Farm, Ongar Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Feb 2025 | Dec 2024 | granted Feb 2025 | Feb 2025 | Brentwood | 9.2 |
Distance from the average position of the CM4 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 10 | 0 | 5 | 3 | 1 | 57 |
| Rooftop solar | 2 | 0 | 2 | 0 | 0 | 0.3 |
| Battery storage | 8 | 1 | 4 | 2 | 1 | 50.5 |
MW in pipeline: pending, approved and under-construction capacity.
How Brentwood decides solar, wind and battery applications
Brentwood has 9 decided solar, wind or battery applications in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near CM4, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.