Energy Projects Near You

Solar, wind and battery projects near Brentwood (CM14)

33 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of CM14 (Brentwood): 3 are waiting for a planning decision, 16 approved but not yet running, 10 operational. The largest live scheme is Lower Dunton Road (368 MW battery storage, application submitted on 25 October 2024, no decision recorded), 9.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

33projects within 10 km
3awaiting a decision
16approved, not running
10operational

Projects within 10 km of CM14

Projects of 1 MW and more (23)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Solar Farm at Billericay Solar Farm North Of Rayleigh Road Huttonsolar farmsolar farm15approved, not builtupdated Nov 2025Nov 2024granted Apr 2025Nov 2025Brentwood3.2
Hutton Battery Storage (Lower Road)battery storagebattery storage10operationalupdated Mar 2026Sep 2017granted Dec 2017Mar 2026Brentwood5.0
Brentwood nergy Storage Systembattery storagebattery storage49.9approved, not built may be out of dateupdated Jul 2022Dec 2020granted May 2021Jul 2022Brentwood5.4
Land at Havering Grove Farmsolar farmsolar farm5refused on appealupdated May 2016Feb 2015refused Jun 2015May 2016Brentwood6.2
Crouch Solar Farmsolar farmsolar farm49.9operationalupdated Oct 2024May 2021granted Dec 2021Oct 2024Brentwood6.7
Crouch Solar Farmbattery storagebattery storage49.9operationalupdated Oct 2024May 2021granted Dec 2021Oct 2024Brentwood6.7
Cranham Golf Course Solar Parksolar farmsolar farm2.6operationalupdated Feb 2017Jun 2014granted Aug 2015Feb 2017Havering6.7
Cranham Golf Coursesolar farmsolar farm2.6refusedupdated Feb 2015Nov 2014refused Jan 2015Feb 2015Havering6.7
Clay Tye Farmsolar farmsolar farm15.9refusedupdated May 2016Sep 2014refused Jan 2015May 2016Havering6.9
Great Cowbridge Grange Farm, London Road Solar Farmsolar farmsolar farm10approved, not builtupdated May 2025Sep 2024granted May 2025May 2025Basildon7.0
Clay Tye Farm Energy Storage Facilitybattery storagebattery storage200application submittedupdated Jul 2026May 2026—Jul 2026Havering7.4
Clay Tye Farm Phase 1 - Storage Facilitybattery storagebattery storage49.5operationalupdated Mar 2024Apr 2017granted Mar 2023Mar 2024Havering7.4
Clay Tye Farm Phase 2 - Storage Facilitybattery storagebattery storage49.5operationalupdated Mar 2024Jun 2018granted Feb 2020Mar 2024Havering7.4
Fen Lane, Bulphan Solar Farmsolar farmsolar farm49.9under constructionupdated Mar 2024Jan 2021granted Jul 2021Mar 2024Havering8.9
Ford Research And Engineering Centre, Dunton Solar Farmsolar farmsolar farm5.2operationalupdated Mar 2025Jun 2022granted Feb 2023Mar 2025Basildon8.9
Clay Tye Road Solar Farmsolar farmsolar farm49.9application submitted may be out of dateupdated May 2021Apr 2021—May 2021Thurrock8.9
Ongar Landfill Ground mounted solar photovoltaicsolar farmsolar farm8.8application withdrawnupdated May 2022Feb 2021—May 2022Brentwood8.9
Lower Dunton Road Battery Storage Facilitybattery storagebattery storage28operationalupdated Feb 2026Oct 2020granted Feb 2021Feb 2026Basildon9.0
Lower Dunton Roadbattery storagebattery storage368application submittedupdated Nov 2024Oct 2024—Nov 2024Basildon9.0
Fairwind Farmsolar farmsolar farm10operationalupdated Jul 2015Jun 2013granted Nov 2013Jul 2015Basildon9.1
Bulphan Fen Solar Farm & Battery Storagesolar farmsolar farm49.9under constructionupdated Jul 2025Jan 2021granted Oct 2021Jul 2025Thurrock9.4
Lime Kilns Energy Centrebattery storagebattery storage6approved, not builtupdated Jul 2025Oct 2024granted Dec 2024Jul 2025Thurrock9.8
Solar Farm at Nickerlandssolar farmsolar farm25approved, not builtupdated Feb 2026Aug 2024granted Feb 2025Feb 2026Epping Forest9.9
Smaller schemes under 1 MW, mostly rooftop solar (10)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
The Marillac, Eagle Wayrooftop solarrooftop solar0.2approved, not builtupdated Jul 2025Apr 2025granted Jun 2025Jul 2025Brentwood2.2
Peri Limited, Greenways Solar Photovoltaicsrooftop solarrooftop solar0.5approved, not builtupdated Jan 2023Nov 2022granted Dec 2022Jan 2023Brentwood4.3
Central Park Leisurerooftop solarrooftop solar0.4approved, not builtupdated Jan 2025Oct 2024granted Nov 2024Jan 2025Havering4.7
Romford Halal Meats, Folkes Lanerooftop solarrooftop solar0.2approved, not built may be out of dateupdated Jan 2023Sep 2022granted Dec 2022Jan 2023Havering4.9
David Lloyd Leisure, Gidea Parkrooftop solarrooftop solar0.4approved, not builtupdated Aug 2023Jun 2023granted Jul 2023Aug 2023Havering6.4
Warley Energy Hub, Ockendenbattery storagebattery storage0.2approved, not builtupdated Sep 2025Nov 2024granted Aug 2025Sep 2025Havering6.6
Bower Park Academyrooftop solarrooftop solar0.3operationalupdated Dec 2021Jan 2021granted Oct 2021Dec 2021Havering7.8
Langford Bridge Farm, Ongar Roadrooftop solarrooftop solar0.2approved, not builtupdated Feb 2025Dec 2024granted Feb 2025Feb 2025Brentwood8.0
Liberty Shopping Centre, Western Roadrooftop solarrooftop solar0.5approved, not builtupdated Apr 2024Jan 2024granted Mar 2024Apr 2024Havering8.7
Bulphan Fen Solar Farm & Battery Storagebattery storagebattery storage—under constructionupdated Jul 2025Jan 2021granted Oct 2021Jul 2025Thurrock9.4

Distance from the average position of the CM14 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm141543200
Rooftop solar807102.2
Battery storage112450624

MW in pipeline: pending, approved and under-construction capacity.

How Brentwood decides solar, wind and battery applications

Brentwood has 9 decided solar, wind or battery applications in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.

All projects in Brentwood

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near CM14, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.