Energy Projects Near You

Solar Farm at Nickerlands (25 MW)

Solar Farm at Nickerlands is a 25 MW solar farm project in Epping Forest, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 20 February 2025, not yet built; the record was last updated on 20 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

25 MWsolar farm
approved, not builtstatus in REPD
20 February 2026record last updated
Epping Forestcouncil area

Planning timeline

DateStage
2 August 2024Application submitted
20 February 2025Planning permission granted
20 February 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
25 MW
Status (REPD)
approved, not built
Record last updated
20 February 2026
Operator or applicant
AR Toot Hill Limited
Planning authority
Epping Forest
Planning application reference
EPF/1546/24
Site area
26.4 ha
Address (REPD)
Nickerlands, Berwick Lane, Stanford Rivers
Council area (by location)
Epping Forest
Time to decision
29 weeks
Contracts for Difference
AR7a
Name in REPD
Nickerlands Solar Farm - Solar Farm
REPD reference
16550

Who decides

ApplicationsEpping ForestUK
Decided applications (solar, wind, battery)1010,236
Refused3 (30%)19%
Solar refused3 of 912%
Battery storage refused0 of 116%
Median time from submission to decision27.6 weeks17.0 weeks
Appeals lodged / allowed0 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Thrift Solar Farm and BESSsolar farm30approved, not built2.0
Ongar Landfill Ground mounted solar photovoltaicsolar farm8.8application withdrawn4.6
Upland Road - 49.9 Megawatt Solar Panelssolar farm49.9refused7.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6849, 0.1956).