Energy Projects Near You

Solar, wind and battery projects near Ongar (CM5)

7 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of CM5 (Epping Forest): 5 approved but not yet running. The largest live scheme is Thrift Solar Farm and BESS (30 MW solar farm, approved on 24 December 2025, not yet built), 6.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7projects within 10 km
0awaiting a decision
5approved, not running
0operational

Projects within 10 km of CM5

Projects of 1 MW and more (5)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Ongar Landfill Ground mounted solar photovoltaicsolar farmsolar farm8.8application withdrawnupdated May 2022Feb 2021—May 2022Brentwood3.0
Solar Farm at Nickerlandssolar farmsolar farm25approved, not builtupdated Feb 2026Aug 2024granted Feb 2025Feb 2026Epping Forest5.5
Thrift Solar Farm and BESSsolar farmsolar farm30approved, not builtupdated Jan 2026Jun 2025granted Dec 2025Jan 2026Epping Forest6.7
Thrift Solar Farm and BESSbattery storagebattery storage30approved, not builtupdated Jan 2026Jun 2025granted Dec 2025Jan 2026Epping Forest6.7
Upland Road - 49.9 Megawatt Solar Panelssolar farmsolar farm49.9refusedupdated Jul 2026Jul 2025refused Jun 2026Jul 2026Epping Forest9.7
Smaller schemes under 1 MW, mostly rooftop solar (2)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Langford Bridge Farm, Ongar Roadrooftop solarrooftop solar0.2approved, not builtupdated Feb 2025Dec 2024granted Feb 2025Feb 2025Brentwood3.9
Rolls Farm Barns, Hastingwood Roadrooftop solarrooftop solar0.5approved, not builtupdated Mar 2023Oct 2022granted Jan 2023Mar 2023Epping Forest6.1

Distance from the average position of the CM5 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm4020155
Rooftop solar202000.7
Battery storage1010030

MW in pipeline: pending, approved and under-construction capacity.

How Epping Forest decides solar, wind and battery applications

ApplicationsEpping ForestUK
Decided applications (solar, wind, battery)1010,236
Refused3 (30%)19%
Solar refused3 of 912%
Battery storage refused0 of 116%
Median time from submission to decision27.6 weeks17.0 weeks
Appeals lodged / allowed0 / 1—

All projects in Epping Forest

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.