Thrift Solar Farm and BESS (30 MW)

Thrift Solar Farm and BESS is a 30 MW solar farm project in Epping Forest, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 24 December 2025, not yet built; the record was last updated on 13 January 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

30 MWsolar farm
approved, not builtstatus in REPD
13 January 2026record last updated
Epping Forestcouncil area

Planning timeline

DateStage
23 June 2025Application submitted
24 December 2025Planning permission granted

Project details

Technology
solar farm
Capacity
30 MW
Status (REPD)
approved, not built
Record last updated
13 January 2026
Operator or applicant
IB Vogt UK Limited
Planning authority
Epping Forest
Planning application reference
EPF/1216/25
Site area
34.1 ha
Address (REPD)
E/O Tawney Common, Theydon Mount, Epping
Council area (by location)
Epping Forest
Time to decision
26 weeks
REPD reference
18681

The scheme also includes 30 MW of battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsEpping ForestUK
Decided applications (solar, wind, battery)1010,236
Refused3 (30%)19%
Solar refused3 of 912%
Battery storage refused0 of 116%
Median time from submission to decision27.6 weeks17.0 weeks
Appeals lodged / allowed0 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Solar Farm at Nickerlandssolar farm25approved, not built2.0
Upland Road - 49.9 Megawatt Solar Panelssolar farm49.9refused5.6
Ongar Landfill Ground mounted solar photovoltaicsolar farm8.8application withdrawn6.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6894, 0.1674).