Solar, wind and battery projects near Romford (RM4)
20 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of RM4 (Epping Forest): 2 are waiting for a planning decision, 14 approved but not yet running, 1 operational. The largest live scheme is Thrift Solar Farm and BESS (30 MW solar farm, approved on 24 December 2025, not yet built), 5.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of RM4
Projects of 1 MW and more (5)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Thrift Solar Farm and BESSsolar farm | solar farm | 30 | approved, not builtupdated Jan 2026 | Jun 2025 | granted Dec 2025 | Jan 2026 | Epping Forest | 5.4 |
| Thrift Solar Farm and BESSbattery storage | battery storage | 30 | approved, not builtupdated Jan 2026 | Jun 2025 | granted Dec 2025 | Jan 2026 | Epping Forest | 5.4 |
| Solar Farm at Nickerlandssolar farm | solar farm | 25 | approved, not builtupdated Feb 2026 | Aug 2024 | granted Feb 2025 | Feb 2026 | Epping Forest | 5.5 |
| Ongar Landfill Ground mounted solar photovoltaicsolar farm | solar farm | 8.8 | application withdrawnupdated May 2022 | Feb 2021 | — | May 2022 | Brentwood | 9.2 |
| Upland Road - 49.9 Megawatt Solar Panelssolar farm | solar farm | 49.9 | refusedupdated Jul 2026 | Jul 2025 | refused Jun 2026 | Jul 2026 | Epping Forest | 9.9 |
Smaller schemes under 1 MW, mostly rooftop solar (15)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Bower Park Academyrooftop solar | rooftop solar | 0.3 | operationalupdated Dec 2021 | Jan 2021 | granted Oct 2021 | Dec 2021 | Havering | 4.3 |
| Aerzen House, Langston Roadrooftop solar | rooftop solar | 0.1 | approved, not builtupdated Feb 2025 | Nov 2024 | granted Jan 2025 | Feb 2025 | Epping Forest | 4.8 |
| Central Park Leisurerooftop solar | rooftop solar | 0.4 | approved, not builtupdated Jan 2025 | Oct 2024 | granted Nov 2024 | Jan 2025 | Havering | 6.1 |
| Liberty Shopping Centre, Western Roadrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Apr 2024 | Jan 2024 | granted Mar 2024 | Apr 2024 | Havering | 7.2 |
| King George Hospital, Barley Lanerooftop solar | rooftop solar | 0.8 | application submittedupdated Feb 2026 | Jan 2026 | — | Feb 2026 | Redbridge | 7.5 |
| David Lloyd Leisure, Gidea Parkrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Aug 2023 | Jun 2023 | granted Jul 2023 | Aug 2023 | Havering | 7.6 |
| William Torbitt School, Eastern Avenuerooftop solar | rooftop solar | 0.2 | application submitted | May 2026 | — | — | Redbridge | 8.1 |
| Roding Primary School and Nursery, Roding Lane Northrooftop solar | rooftop solar | 0.1 | approved, not built | Apr 2026 | granted Jun 2026 | — | Redbridge | 8.3 |
| Langford Bridge Farm, Ongar Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Feb 2025 | Dec 2024 | granted Feb 2025 | Feb 2025 | Brentwood | 8.5 |
| Barking And Dagenham College, Dagenham Roadrooftop solar | rooftop solar | 0.8 | approved, not builtupdated Jun 2025 | Mar 2025 | granted May 2025 | Jun 2025 | Barking and Dagenham | 9.1 |
| Barking & Dagenham College Of Technology, Dagenham Road Solarrooftop solar | rooftop solar | — | no application requiredupdated May 2025 | Apr 2025 | — | May 2025 | Barking and Dagenham | 9.1 |
| Redbridge Institute Of Adult Education, Gaysham Avenuerooftop solar | rooftop solar | 0.1 | approved, not builtupdated Nov 2025 | Sep 2025 | granted Oct 2025 | Nov 2025 | Redbridge | 9.1 |
| Maybank Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Sep 2025 | Jul 2025 | granted Aug 2025 | Sep 2025 | Redbridge | 9.7 |
| Woodbridge High School, St Barnabas Roadrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Nov 2024 | Sep 2024 | granted Oct 2024 | Nov 2024 | Redbridge | 9.8 |
| Roding Lane Southrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jan 2023 | Oct 2022 | granted Dec 2022 | Jan 2023 | Redbridge | 9.8 |
Distance from the average position of the RM4 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 4 | 0 | 2 | 0 | 1 | 55 |
| Rooftop solar | 15 | 2 | 11 | 1 | 0 | 4.5 |
| Battery storage | 1 | 0 | 1 | 0 | 0 | 30 |
MW in pipeline: pending, approved and under-construction capacity.
How Epping Forest decides solar, wind and battery applications
| Applications | Epping Forest | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 10 | 10,236 |
| Refused | 3 (30%) | 19% |
| Solar refused | 3 of 9 | 12% |
| Battery storage refused | 0 of 1 | 16% |
| Median time from submission to decision | 27.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 1 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.