Solar, wind and battery projects near Epping (CM16)
27 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of CM16 (Epping Forest): 22 approved but not yet running, 1 operational. The largest live scheme is East End Solar Farm (49.9 MW solar farm, approved on 3 May 2024, not yet built), 9.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of CM16
Projects of 1 MW and more (9)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Upland Road - 49.9 Megawatt Solar Panelssolar farm | solar farm | 49.9 | refusedupdated Jul 2026 | Jul 2025 | refused Jun 2026 | Jul 2026 | Epping Forest | 2.7 |
| Thrift Solar Farm and BESSsolar farm | solar farm | 30 | approved, not builtupdated Jan 2026 | Jun 2025 | granted Dec 2025 | Jan 2026 | Epping Forest | 3.5 |
| Thrift Solar Farm and BESSbattery storage | battery storage | 30 | approved, not builtupdated Jan 2026 | Jun 2025 | granted Dec 2025 | Jan 2026 | Epping Forest | 3.5 |
| Solar Farm at Nickerlandssolar farm | solar farm | 25 | approved, not builtupdated Feb 2026 | Aug 2024 | granted Feb 2025 | Feb 2026 | Epping Forest | 5.5 |
| Poundland Distribution Centrerooftop solar | rooftop solar | 1.5 | approved, not built may be out of dateupdated Jun 2022 | Jun 2022 | granted Jul 2022 | Jun 2022 | Harlow | 8.3 |
| Waltham Point Distribution Centrerooftop solar | rooftop solar | 1.8 | operationalupdated May 2016 | — | — | May 2016 | Epping Forest | 9.2 |
| West Essex Golf Club, Bury Road Solar Farmsolar farm | solar farm | 10.7 | refused on appealupdated Dec 2025 | Nov 2023 | refused Nov 2025 | Dec 2025 | Epping Forest | 9.4 |
| East End Solar Farmsolar farm | solar farm | 49.9 | approved, not builtupdated Feb 2026 | Aug 2022 | granted May 2024 | Feb 2026 | Epping Forest | 9.4 |
| Ongar Landfill Ground mounted solar photovoltaicsolar farm | solar farm | 8.8 | application withdrawnupdated May 2022 | Feb 2021 | — | May 2022 | Brentwood | 9.6 |
Smaller schemes under 1 MW, mostly rooftop solar (18)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Aerzen House, Langston Roadrooftop solar | rooftop solar | 0.1 | approved, not builtupdated Feb 2025 | Nov 2024 | granted Jan 2025 | Feb 2025 | Epping Forest | 6.3 |
| Rolls Farm Barns, Hastingwood Roadrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Mar 2023 | Oct 2022 | granted Jan 2023 | Mar 2023 | Epping Forest | 6.5 |
| Icon Harlow, Third Avenuerooftop solar | rooftop solar | 0.7 | approved, not builtupdated Jul 2023 | May 2023 | granted Jun 2023 | Jul 2023 | Harlow | 7.3 |
| Icon Industrial Estaterooftop solar | rooftop solar | 0.5 | approved, not builtupdated Jun 2023 | Apr 2023 | granted Jun 2023 | Jun 2023 | Harlow | 7.4 |
| Icon Harlow, Gsk Third Avenuerooftop solar | rooftop solar | 0.6 | refusedupdated Sep 2023 | Jul 2023 | refused Sep 2023 | Sep 2023 | Harlow | 7.6 |
| Harlow Leisurezone, Second Avenuerooftop solar | rooftop solar | 0.7 | approved, not builtupdated May 2024 | Mar 2024 | granted Apr 2024 | May 2024 | Harlow | 7.6 |
| Gsk Icon Harlowrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Nov 2023 | Sep 2023 | granted Nov 2023 | Nov 2023 | Harlow | 7.6 |
| Icon Harlow, Unit Brooftop solar | rooftop solar | 0.8 | approved, not builtupdated Jul 2023 | May 2023 | granted Jun 2023 | Jul 2023 | Harlow | 7.7 |
| Icon Harlow, Unit Crooftop solar | rooftop solar | 0.6 | approved, not builtupdated Jul 2023 | May 2023 | granted Jun 2023 | Jul 2023 | Harlow | 7.7 |
| Wrights Flour Mills, Roydon Roadrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Jul 2023 | May 2023 | granted Jul 2023 | Jul 2023 | Harlow | 8.5 |
| West Road - Micro Energy Storage Facilitybattery storage | battery storage | 0.2 | approved, not builtupdated Jul 2026 | Mar 2026 | granted Jun 2026 | Jul 2026 | Harlow | 9.2 |
| Calder House, Central Roadrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Dec 2022 | Oct 2022 | granted Dec 2022 | Dec 2022 | Harlow | 9.4 |
| Edinburgh Wayrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2026 | Jan 2026 | granted Mar 2026 | May 2026 | Harlow | 9.5 |
| Langford Bridge Farm, Ongar Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Feb 2025 | Dec 2024 | granted Feb 2025 | Feb 2025 | Brentwood | 9.6 |
| Gates Of Harlow, Edinburgh Waysolar farm | solar farm | 0.2 | approved, not builtupdated Apr 2022 | Apr 2022 | granted May 2022 | Apr 2022 | Harlow | 9.7 |
| The Scout Association, Gilwell Parkrooftop solar | rooftop solar | 0.1 | approved, not builtupdated Jan 2026 | Oct 2025 | granted Nov 2025 | Jan 2026 | Epping Forest | 9.9 |
| Gilwell Park, Bury Roadsolar farm | solar farm | 0.6 | approved, not builtupdated Jun 2024 | Apr 2023 | granted May 2024 | Jun 2024 | Epping Forest | 9.9 |
| Fibron B X, Rd Parkrooftop solar | rooftop solar | 0.7 | approved, not builtupdated Jul 2025 | May 2025 | granted Jul 2025 | Jul 2025 | Broxbourne | 9.9 |
Distance from the average position of the CM16 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 8 | 0 | 5 | 0 | 2 | 106 |
| Rooftop solar | 17 | 0 | 15 | 1 | 1 | 8.2 |
| Battery storage | 2 | 0 | 2 | 0 | 0 | 30.2 |
MW in pipeline: pending, approved and under-construction capacity.
How Epping Forest decides solar, wind and battery applications
| Applications | Epping Forest | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 10 | 10,236 |
| Refused | 3 (30%) | 19% |
| Solar refused | 3 of 9 | 12% |
| Battery storage refused | 0 of 1 | 16% |
| Median time from submission to decision | 27.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 1 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near CM16, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.