West Essex Golf Club, Bury Road Solar Farm (10.7 MW)

West Essex Golf Club, Bury Road Solar Farm is a 10.7 MW solar farm project in Epping Forest, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 4 November 2025; the record was last updated on 16 December 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10.7 MWsolar farm
refused on appealstatus in REPD
16 December 2025record last updated
Epping Forestcouncil area

Planning timeline

DateStage
27 November 2023Application submitted
4 November 2025Refused by the planning authority
4 November 2025Appeal refused

Project details

Technology
solar farm
Capacity
10.7 MW
Status (REPD)
refused on appeal
Record last updated
16 December 2025
Operator or applicant
West Essex GC Green Energy Limited
Planning authority
Epping Forest
Planning application reference
EPF/2596/23
Site area
11.2 ha
Address (REPD)
West Essex Golf Club Limited, Bury Road, Chingford
Council area (by location)
Epping Forest
Time to decision
101 weeks
Name in REPD
West Essex Golf Club, Bury Road - Solar Farm
REPD reference
14209

Who decides

ApplicationsEpping ForestUK
Decided applications (solar, wind, battery)1010,236
Refused3 (30%)19%
Solar refused3 of 912%
Battery storage refused0 of 116%
Median time from submission to decision27.6 weeks17.0 weeks
Appeals lodged / allowed0 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
St Marys C Of E Va High School, Lieutenant Ellis Wayrooftop solar8.8approved, not built6.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6506, 0.0112).