Energy Projects Near You

Solar, wind and battery projects near London (E4)

49 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of E4 (Waltham Forest): 7 are waiting for a planning decision, 35 approved but not yet running, 3 operational. The largest live scheme is St Marys C Of E Va High School, Lieutenant Ellis Way (8.8 MW rooftop solar, approved on 1 July 2025, not yet built), 9.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49projects within 10 km
7awaiting a decision
35approved, not running
3operational

Projects within 10 km of E4

Projects of 1 MW and more (5)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
West Essex Golf Club, Bury Road Solar Farmsolar farmsolar farm10.7refused on appealupdated Dec 2025Nov 2023refused Nov 2025Dec 2025Epping Forest3.4
Iceland, Solar Wayrooftop solarrooftop solar2.6approved, not builtupdated Feb 2024Oct 2023granted Jan 2024Feb 2024Enfield6.2
Waltham Point Distribution Centrerooftop solarrooftop solar1.8operationalupdated May 2016——May 2016Epping Forest6.4
St Marys C Of E Va High School, Lieutenant Ellis Wayrooftop solarrooftop solar8.8approved, not builtupdated Jul 2025May 2025granted Jul 2025Jul 2025Broxbourne9.0
Olympic Park Wind Turbinewind turbinewind turbine2.5abandonedupdated Oct 2010Jan 2007granted Sep 2007Oct 2010Newham9.3
Smaller schemes under 1 MW, mostly rooftop solar (44)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Woodford County High Schoolrooftop solarrooftop solar0.3application withdrawnupdated Jun 2026Feb 2026—Jun 2026Waltham Forest2.3
Eley Roadrooftop solarrooftop solar0.3approved, not builtupdated Apr 2022Apr 2022granted Jun 2022Apr 2022Enfield2.9
Advent Wayrooftop solarrooftop solar0.2operationalupdated Jan 2022Sep 2021granted Nov 2021Jan 2022Enfield3.0
Workstown Industrial Estate, Princes Roadrooftop solarrooftop solar0.3approved, not builtupdated Aug 2023Jun 2023granted Aug 2023Aug 2023Enfield3.0
Gilwell Park, Bury Roadsolar farmsolar farm0.6approved, not builtupdated Jun 2024Apr 2023granted May 2024Jun 2024Epping Forest3.2
The Scout Association, Gilwell Parkrooftop solarrooftop solar0.1approved, not builtupdated Jan 2026Oct 2025granted Nov 2025Jan 2026Epping Forest3.2
Churchfields Junior School, Churchfieldsrooftop solarrooftop solar0.2approved, not builtupdated Oct 2023Aug 2023granted Oct 2023Oct 2023Redbridge3.3
Woodbridge High School, St Barnabas Roadrooftop solarrooftop solar0.5approved, not builtupdated Nov 2024Sep 2024granted Oct 2024Nov 2024Redbridge3.5
Johnson Matthey, Jeffreys Roadrooftop solarrooftop solar0.7application submittedMay 2026——Enfield3.6
Delta Park Industrial Estate, Millmarsh Lanerooftop solarrooftop solar0.3approved, not builtupdated Jul 2023Jun 2023granted Jul 2023Jul 2023Enfield3.9
Compass West Estate, West Roadrooftop solarrooftop solar0.2application submitted may be out of dateupdated Jul 2024Jun 2024—Jul 2024Haringey4.0
Maybank Roadrooftop solarrooftop solar0.2approved, not builtupdated Sep 2025Jul 2025granted Aug 2025Sep 2025Redbridge4.0
Heron Hall Academyrooftop solarrooftop solar0.1approved, not built may be out of dateupdated Mar 2022Mar 2022granted Jun 2022Mar 2022Enfield4.1
Lockfield Avenue Solarrooftop solarrooftop solar0.2under constructionupdated Apr 2021Oct 2020granted Dec 2020Apr 2021Enfield4.4
Edmonton County School, Great Cambridge Roadrooftop solarrooftop solar0.3approved, not builtupdated Jan 2024Nov 2023granted Jan 2024Jan 2024Enfield4.5
Southbury Roadrooftop solarrooftop solar0.3refusedupdated Oct 2024Aug 2024refused Oct 2024Oct 2024Enfield4.6
Southbury Roadrooftop solarrooftop solar0.2approved, not builtupdated Jan 2025Oct 2024granted Nov 2024Jan 2025Enfield4.6
Roding Primary School and Nursery, Roding Lane Northrooftop solarrooftop solar0.1approved, not builtApr 2026granted Jun 2026—Redbridge4.7
Nightingale Primary School, Ashbourne Avenue -Solar Panelsrooftop solarrooftop solar0.2approved, not builtupdated Jul 2025May 2025granted Jun 2025Jul 2025Redbridge4.9
Roding Lane Southrooftop solarrooftop solar0.2approved, not builtupdated Jan 2023Oct 2022granted Dec 2022Jan 2023Redbridge4.9
Chalkmill Driverooftop solarrooftop solar0.5application submittedMay 2026——Enfield4.9
The Arenarooftop solarrooftop solar0.5approved, not builtupdated Aug 2024Jun 2024granted Aug 2024Aug 2024Enfield5.0
The Arenarooftop solarrooftop solar0.5approved, not builtupdated Aug 2024Jun 2024granted Aug 2024Aug 2024Enfield5.0
Sainsburys Supermarketsrooftop solarrooftop solar0.7approved, not builtupdated Apr 2025Jan 2025granted Mar 2025Apr 2025Enfield5.0
Spire London East Hospital, Roding Lane Southrooftop solarrooftop solar0.2approved, not builtupdated Sep 2024Jul 2024granted Sep 2024Sep 2024Redbridge5.1
Edmonton lower schoolrooftop solarrooftop solar0.2approved, not builtupdated Mar 2024Jan 2024granted Mar 2024Mar 2024Enfield5.2
Coppermill Workssolar farmsolar farm0.7application submitted may be out of dateupdated Aug 2022Jul 2022—Aug 2022Waltham Forest5.4
Solar Panels at 7 Solar Wayrooftop solarrooftop solar0.4approved, not builtupdated May 2024Oct 2023granted May 2024May 2024Enfield6.2
Sainsburys Supermarkets, Green Lanesrooftop solarrooftop solar0.2approved, not builtupdated Mar 2025Feb 2025granted Apr 2025Mar 2025Enfield6.4
Enfield County School For Girls, Holly Walkrooftop solarrooftop solar0.2application submittedMay 2026——Enfield6.5
Redbridge Institute Of Adult Education, Gaysham Avenuerooftop solarrooftop solar0.1approved, not builtupdated Nov 2025Sep 2025granted Oct 2025Nov 2025Redbridge7.1
Aerzen House, Langston Roadrooftop solarrooftop solar0.1approved, not builtupdated Feb 2025Nov 2024granted Jan 2025Feb 2025Epping Forest7.2
New Spitalfields Market, Allen Houserooftop solarrooftop solar0.2approved, not builtupdated Jun 2026Feb 2026granted Apr 2026Jun 2026Waltham Forest7.4
Wood Green Shopping City, High Roadrooftop solarrooftop solar0.3approved, not builtupdated May 2026Jan 2026granted Mar 2026May 2026Haringey7.8
Homerton University Hospital, Homerton Groverooftop solarrooftop solar0.3approved, not builtupdated Apr 2026Jan 2026granted Feb 2026Apr 2026Hackney8.4
University Of East London, Stratford Cam PV Panelsrooftop solarrooftop solar0.2approved, not builtupdated Apr 2024Jan 2024granted Mar 2024Apr 2024Newham8.6
William Torbitt School, Eastern Avenuerooftop solarrooftop solar0.2application submittedMay 2026——Redbridge8.7
Westfield Stratford City, Montfichet Roadrooftop solarrooftop solar0.3approved, not builtupdated Aug 2023Jun 2023granted Aug 2023Aug 2023Newham8.7
The Exchange Mall, High Roadrooftop solarrooftop solar0.7approved, not builtupdated Dec 2024Oct 2024granted Nov 2024Dec 2024Redbridge8.7
University Of East London - 650 Student accommodation & Teaching and learningrooftop solarrooftop solar0.2under constructionupdated Jun 2026Apr 2023granted Aug 2025Jun 2026Newham8.8
Ashmole Academy, Cecil Roadrooftop solarrooftop solar0.3approved, not builtupdated Jun 2026Mar 2026granted May 2026Jun 2026Barnet9.1
King George Hospital, Barley Lanerooftop solarrooftop solar0.8application submittedupdated Feb 2026Jan 2026—Feb 2026Redbridge9.3
Plashet Schoolrooftop solarrooftop solar0.2approved, not builtupdated Aug 2025May 2025granted Jul 2025Aug 2025Newham9.9
Holly Streetrooftop solarrooftop solar0.2operationalupdated Jan 2022Aug 2021granted Feb 2023Jan 2022Hackney9.9

Distance from the average position of the E4 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm311011.3
Rooftop solar456343123.2
Wind turbine100000

MW in pipeline: pending, approved and under-construction capacity.

How Waltham Forest decides solar, wind and battery applications

Waltham Forest has 3 decided solar, wind or battery applications in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.

All projects in Waltham Forest

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near E4, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.