Land at Havering Grove Farm (5 MW solar farm)

Land at Havering Grove Farm is a 5 MW solar farm project in Brentwood, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 23 May 2016; the record was last updated on 30 May 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
refused on appealstatus in REPD
30 May 2016record last updated
Brentwoodcouncil area

Planning timeline

DateStage
16 February 2015Application submitted
26 June 2015Refused by the planning authority
28 October 2015Appeal lodged
23 May 2016Appeal refused

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
refused on appeal
Record last updated
30 May 2016
Operator or applicant
Lightsource Renewable Energy
Planning authority
Brentwood
Planning application reference
15/00161/FUL
Appeal reference
APP/H1515/W/15/3134301
Site area
8.1 ha
Address (REPD)
Land at Havering Grove Farm, 552A Rayleigh Road, Hutton
Council area (by location)
Brentwood
Time to decision
19 weeks
REPD reference
4803

Who decides

Brentwood has 9 decided solar, wind or battery applications in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.

Other large projects within 10 km

ProjectTypeMWStatuskm
Great Cowbridge Grange Farm, London Road Solar Farmsolar farm10approved, not built0.8
Brentwood nergy Storage Systembattery storage49.9approved, not built1.9
Hutton Battery Storage (Lower Road)battery storage10operational1.9
Solar Farm at Billericay Solar Farm North Of Rayleigh Road Huttonsolar farm15approved, not built3.4
Crouch Solar Farmsolar farm49.9operational4.2
Outwood Farm (Phase 1)solar farm5operational4.6
Outwood Farm (Phase 2)solar farm7approved, not built4.6
Barleylands Solar Farmsolar farm17approved, not built5.4
Ford Research And Engineering Centre, Dunton Solar Farmsolar farm5.2operational5.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6281, 0.3804).