Outwood Farm (Phase 1) (5 MW solar farm)

Outwood Farm (Phase 1) is a 5 MW solar farm project in Basildon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 30 March 2016; the record was last updated on 1 July 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
1 July 2016record last updated
Basildoncouncil area

Planning timeline

DateStage
7 August 2014Application submitted
11 December 2014Planning permission granted
1 November 2015Construction started
30 March 2016Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
1 July 2016
Operator or applicant
MS Power Projects
Planning authority
Basildon
Planning application reference
14/00948/FULL
Site area
24.6 ha
Address (REPD)
Land At Outwood Farm Road Billericay, Essex
Council area (by location)
Basildon
Time to decision
18 weeks
REPD reference
2240

Who decides

ApplicationsBasildonUK
Decided applications (solar, wind, battery)2010,236
Refused2 (10%)19%
Solar refused1 of 1212%
Battery storage refused1 of 816%
Median time from submission to decision16.8 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Outwood Farm (Phase 2)solar farm7approved, not built<0.1
Crays Hall Farm Solar Arrayssolar farm25.6operational2.0
Barleylands Solar Farmsolar farm17approved, not built2.3
Whites Farmbattery storage49.9refused2.9
Great Cowbridge Grange Farm, London Road Solar Farmsolar farm10approved, not built3.8
Nevendonbattery storage10operational4.6
Nevendon Battery Storage Extensionbattery storage5operational4.6
Land at Havering Grove Farmsolar farm5refused on appeal4.6
Ford Research And Engineering Centre, Dunton Solar Farmsolar farm5.2operational5.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6219, 0.4467).