Crays Hall Farm Solar Arrays (25.6 MW)

Crays Hall Farm Solar Arrays is a 25.6 MW solar farm project in Basildon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 14 May 2026; the record was last updated on 3 June 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

25.6 MWsolar farm
operationalstatus in REPD
3 June 2026record last updated
Basildoncouncil area

Planning timeline

DateStage
1 March 2022Application submitted
8 March 2023Appeal lodged
30 August 2023Refused by the planning authority
30 August 2023Planning permission granted
30 August 2023Appeal allowed
1 August 2025Construction started
14 May 2026Operational

Project details

Technology
solar farm
Capacity
25.6 MW
Status (REPD)
operational
Record last updated
3 June 2026
Operator or applicant
Boom Power Limited
Planning authority
Basildon
Planning application reference
22/00296/FULL
Appeal reference
23/00016/REFUSE
Site area
44.2 ha
Address (REPD)
Crays Hall Farm Church Lane Ramsden Crays Billericay
Council area (by location)
Basildon
Time to decision
78 weeks
Contracts for Difference
AR6
Name in REPD
Crays Hall Farm - Solar Arrays
REPD reference
10778

Who decides

ApplicationsBasildonUK
Decided applications (solar, wind, battery)2010,236
Refused2 (10%)19%
Solar refused1 of 1212%
Battery storage refused1 of 816%
Median time from submission to decision16.8 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Barleylands Solar Farmsolar farm17approved, not built1.8
Outwood Farm (Phase 2)solar farm7approved, not built2.0
Outwood Farm (Phase 1)solar farm5operational2.0
Whites Farmbattery storage49.9refused2.0
Nevendon Battery Storage Extensionbattery storage5operational2.6
Nevendonbattery storage10operational2.6
Rayleigh Spur Roundabout, Benfleetbattery storage150application submitted4.9
Ford Research And Engineering Centre, Dunton Solar Farmsolar farm5.2operational5.3
Great Cowbridge Grange Farm, London Road Solar Farmsolar farm10approved, not built5.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6096, 0.4672).