Energy Projects Near You

Nevendon (10 MW battery storage)

Nevendon is a 10 MW battery storage project in Basildon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 March 2018; the record was last updated on 28 March 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWbattery storage
operationalstatus in REPD
28 March 2017record last updated
Basildoncouncil area

Planning timeline

DateStage
15 March 2018Operational
15 October 2018Construction started

Project details

Technology
battery storage (stand-alone storage)
Capacity
10 MW
Status (REPD)
operational
Record last updated
28 March 2017
Operator or applicant
Belectric UK / Foresight
Planning authority
Basildon
Planning application reference
not recorded
Address (REPD)
Nevendon,
Council area (by location)
Basildon
REPD reference
6926

Who decides

ApplicationsBasildonUK
Decided applications (solar, wind, battery)2010,236
Refused2 (10%)19%
Solar refused1 of 1212%
Battery storage refused1 of 816%
Median time from submission to decision16.8 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Nevendon Battery Storage Extensionbattery storage5operational<0.1
Crays Hall Farm Solar Arrayssolar farm25.6operational2.6
Rayleigh Spur Roundabout, Benfleetbattery storage150application submitted3.1
Whites Farmbattery storage49.9refused3.2
Barleylands Solar Farmsolar farm17approved, not built3.5
Outwood Farm (Phase 1)solar farm5operational4.6
Outwood Farm (Phase 2)solar farm7approved, not built4.6
Southlands Solar Farm & Battery Storagesolar farm24.6approved, not built4.6
Dollymans Storagebattery storage100operational4.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.5933, 0.4949).