Energy Projects Near You

Ford Research And Engineering Centre, Dunton Solar Farm (5.2 MW)

Ford Research And Engineering Centre, Dunton Solar Farm is a 5.2 MW solar farm project in Basildon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 January 2025; the record was last updated on 3 March 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5.2 MWsolar farm
operationalstatus in REPD
3 March 2025record last updated
Basildoncouncil area

Planning timeline

DateStage
10 June 2022Application submitted
28 February 2023Planning permission granted
1 November 2024Construction started
31 January 2025Operational

Project details

Technology
solar farm
Capacity
5.2 MW
Status (REPD)
operational
Record last updated
3 March 2025
Operator or applicant
Ford Motor Company Limited
Planning authority
Basildon
Planning application reference
22/00748/FULL
Site area
6.9 ha
Address (REPD)
Ford Research And Engineering Centre West Mayne Dunton Basildon
Council area (by location)
Basildon
Time to decision
38 weeks
Name in REPD
Ford Research And Engineering Centre, Dunton - Solar Farm
REPD reference
11486

Who decides

ApplicationsBasildonUK
Decided applications (solar, wind, battery)2010,236
Refused2 (10%)19%
Solar refused1 of 1212%
Battery storage refused1 of 816%
Median time from submission to decision16.8 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Lower Dunton Roadbattery storage368application submitted1.8
Lower Dunton Road Battery Storage Facilitybattery storage28operational1.9
Fairwind Farmsolar farm10operational2.2
Crouch Solar Farmsolar farm49.9operational2.2
Lime Kilns Energy Centrebattery storage6approved, not built2.8
Whites Farmbattery storage49.9refused3.4
Barleylands Solar Farmsolar farm17approved, not built3.5
Great Cowbridge Grange Farm, London Road Solar Farmsolar farm10approved, not built5.2
Crays Hall Farm Solar Arrayssolar farm25.6operational5.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.5814, 0.4053).