Land adjacent to the former Coryton Refinery (5 MW solar farm)

Land adjacent to the former Coryton Refinery is a 5 MW solar farm project in Thurrock, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 24 November 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
abandonedstatus in REPD
24 November 2017record last updated
Thurrockcouncil area

Planning timeline

DateStage
22 September 2015Application submitted
12 February 2016Planning permission granted
12 February 2019Permission expired

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
abandoned
Record last updated
24 November 2017
Operator or applicant
S4N Worsted/Gamma Energy Exeter
Planning authority
Thurrock
Planning application reference
15/00877/FUL
Site area
8.0 ha
Address (REPD)
Petroplus Land Part Of Area, 418 Coryton Refinery, The Manorway, Stanford-Le-Hope, Essex, East of England
Council area (by location)
Thurrock
Time to decision
20 weeks
REPD reference
5922

Who decides

ApplicationsThurrockUK
Decided applications (solar, wind, battery)2810,236
Refused3 (11%)19%
Solar refused2 of 1812%
Onshore wind refused0 of 245%
Battery storage refused1 of 816%
Median time from submission to decision20.3 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Gateway Energy Centrebattery storage450approved, not built1.8
Marsh Farm, Fobbing Solar Arrays & Battery Storagesolar farm49.9application withdrawn2.3
Nevendonbattery storage10operational7.8
Nevendon Battery Storage Extensionbattery storage5operational7.8
Barvills Solar Farmsolar farm5operational8.2
Dollymans Storagebattery storage100operational8.7
Tilbury Energy Centrebattery storage100abandoned8.8
Lime Kilns Energy Centrebattery storage6approved, not built8.8
Rayleigh Spur Roundabout, Benfleetbattery storage150application submitted8.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.5237, 0.5087).