Energy Projects Near You

Gateway Energy Centre (450 MW battery storage)

Gateway Energy Centre is a 450 MW battery storage project in Thurrock, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 13 January 2023, not yet built; the record was last updated on 17 December 2021.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

450 MWbattery storage
approved, not builtstatus in REPD
17 December 2021record last updated
Thurrockcouncil area

Planning timeline

DateStage
17 November 2021Application submitted
13 January 2023Planning permission granted
13 January 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
450 MW
Status (REPD)
approved, not built
Record last updated
17 December 2021
Operator or applicant
Intergen Limited
Planning authority
Thurrock
Planning application reference
21/01971/FUL
Address (REPD)
East 2 Baltic Avenue Stanford Le Hope
Council area (by location)
Thurrock
Time to decision
60 weeks
Name in REPD
Gateway Energy Centre - Battery Energy Storage
REPD reference
10309

Who decides

ApplicationsThurrockUK
Decided applications (solar, wind, battery)2810,236
Refused3 (11%)19%
Solar refused2 of 1812%
Onshore wind refused0 of 245%
Battery storage refused1 of 816%
Median time from submission to decision20.3 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land adjacent to the former Coryton Refinerysolar farm5abandoned1.8
Marsh Farm, Fobbing Solar Arrays & Battery Storagesolar farm49.9application withdrawn2.3
Barvills Solar Farmsolar farm5operational6.5
Tilbury Energy Centrebattery storage100abandoned7.0
Lime Kilns Energy Centrebattery storage6approved, not built8.8
Nevendonbattery storage10operational9.3
Nevendon Battery Storage Extensionbattery storage5operational9.3
Fairwind Farmsolar farm10operational9.4
Lower Dunton Roadbattery storage368application submitted9.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.5101, 0.4951).